Question · Q3 2025
Alex Rygiel from Texas Capital Securities asked if Sterling Infrastructure generally experiences permitting issues that could delay project starts, noting that the process is longer than pre-COVID. He also inquired about any 'green shoots' or signs of improvement within the building solutions segment that might indicate a recovery starting in 2026.
Answer
Joe Cutillo, CEO, confirmed that the permitting process is significantly longer than pre-COVID (e.g., 6 weeks now taking 3-5 months), delaying project starts before contracts are finalized. He stated that while this is a 'long pole in the tent' for accelerating onshoring/reshoring, Sterling typically sees delays before equipment is on-site. Regarding building solutions, Cutillo indicated that the market has flattened and is not worsening, but he does not anticipate an uptick until the second half of 2026 at the earliest, even with potential interest rate declines and builder programs.