Question · Q4 2025
Alexander Bidwell from Webber Research and Advisory asked about the expected future production levels of the Gimi FLNG above its contractual base, considering factors like ambient temperature, gas composition, and maintenance. He also requested a detailed explanation of the startup and commissioning cadence for the Hilli and Mark II FLNGs in Argentina, including lessons learned from previous deployments in Cameroon and GTA.
Answer
CEO Karl Fredrik Staubo clarified that scheduled maintenance is already factored into Gimi's contractual capacity, anticipating seasonal production variations but consistently above the contracted amount annually. For Argentina, he projected Hilli's commissioning to take 3-4 months and Mark II's up to 6 months. A key lesson from Hilli and Gimi deployments, likely to be applied, is arriving 'cold' with LNG on tanks to expedite commissioning before pipeline gas connection.
Ask follow-up questions
Fintool can predict
GLNG's earnings beat/miss a week before the call