Craig Stanley's questions to ENDEAVOUR SILVER (EXK) leadership • Q2 2025
Question
Craig Stanley asked about the operational performance of the new filter presses at Terronera. He also requested updated timelines for the initial 43-101 technical report for Culpa and the next economic study for the Pitorrhea project.
Answer
CEO Dan Dickson and COO Donald Gray both reported that the filter presses at Terronera are working 'really, really well' and more smoothly than anticipated. For Culpa, Dickson estimated an initial resource report would likely be ready by mid-2026. He noted that the timeline for an updated Pitorrhea study is now likely beyond early 2026, as the immediate focus has shifted to securing the crucial tailings dam permit.