Question · Q3 2025
Dillon asked about the progress in securing long lead time items for the 1.5 GW expansion initiative to improve build time visibility across the four sites.
Answer
CEO Asher Genoot confirmed that all four sites have land control and utility agreements, with power available before development. He noted increased reserves of long lead time items like high-to-medium voltage breakers and a design strategy using common equipment across sites for malleability and risk reduction.