Eric Boyes requested a timeline update on the startup of Linde's unit at TSMC's Arizona Fab 2 and asked how gas intensity increases from Fab 1 to Fab 2, impacting Linde's profitability.
Answer
Sanjiv Lamba, CEO, confirmed that Linde's plants for TSMC's Arizona Fab 1 and Fab 2 are already in operation, commissioned, and in various stages of utilization, with Fab 2 ramping up as planned. He explained that advanced nodes lead to higher gas intensity, meaning increased usage of existing gases per node and the introduction of new gases in larger quantities, all contributing to an overall increase in gas intensity for these new fabs.