Question · Q4 2025
Garrett Roberts asked about the future potential build-out at Helios, specifically the recent 830 MW incremental approval from ERCOT, how that study went, any constraints encountered, and the expected process for the two additional 1.8 GW applications.
Answer
President and Chief Investment Officer Christopher C. Ferraro explained that the 830 MW approval was part of a larger request, concluding the grid could accept it. He noted the 1.8 GW applications would fall under ERCOT's new batch processing, making timing uncertain. CEO Mike Novogratz emphasized the value of securing the 830 MW before the new process, making the power more valuable.