Question · Q4 2025
Myles Allsop inquired about the lead time for the Tia Maria SX-EW operation and the key risks to achieving the mid-2027 first production timeline. He also asked about the local sentiment surrounding Tia Maria, given past protests and upcoming elections, and whether the atmosphere for obtaining mining licenses and approving open-pit projects in Mexico has improved.
Answer
Raul Jacob, VP of Finance, Treasurer, and CFO, stated that Southern Copper has extensive experience with SX-EW operations and has selected state-of-the-art technology for Tia Maria. He expects plant assembly and operation in the second half of 2027, with testing initiated by May or June 2027, and no delays anticipated. Regarding local sentiment, Mr. Jacob highlighted positive engagement with local communities, noting the creation of over 3,589 jobs (with an expectation of 5,000 at peak construction) and significant investments through Peru's 'Works for Taxes' mechanism, which he believes has fostered local understanding of the project's opportunities. For Mexico, he observed a generally better environment in relations with the government, which he hopes will expedite project movement, but had nothing specific to report on new license approvals or open-pit projects.
Ask follow-up questions
Fintool can predict
SCCO's earnings beat/miss a week before the call