Phil Kerr asked for an update on the Bolanitos mill, inquiring if throughput had normalized after recent maintenance. He also asked about the exploration potential at Culpa and the expected timeline for more aggressive exploration efforts there.
Answer
CEO Dan Dixon confirmed that the Bolanitos mill is back to its 1,200 tpd capacity after component replacements caused downtime in Q2. Regarding Culpa, he expressed excitement about the exploration potential, particularly the 'Puerto Rico West' target, and expects to release initial drill results by mid-September. He noted that a $12 million exploration program over 24 months is mandated by the acquisition agreement, ensuring aggressive evaluation.