Question · Q4 2024
Rodrigo Murrieta asked if the company's mid-term production guidance for the El Porvenir and Atacocha mines already incorporates mineralization from the Cerro Pasco integration project.
Answer
SVP of Mining Operations Leonardo Nunes Coelho clarified that the current guidance does not include mineralization from the integration area. It is based only on the current reserve base. He added that the company expects to publish resources for the integration area this year and convert them to reserves by next year, at which point they could be included in the plan.