Question · Q4 2025
Tanya Jakusconek inquired about the implications of the Skouries project delay, specifically how it affects tailings management, benefits from drier weather, the readiness of the ore stockpile, the status of the cyclone feed pump issue, and the progress and regulatory approval timeline for the power line connection.
Answer
George Burns, CEO, explained that the 3-4 month delay provides breathing room for tailings filter installation and other equipment finalization, allowing for more equipment to be ready before first concentrate. He confirmed a significant ore stockpile (over 1.5 million tons) and positive underground development. He detailed the cyclone feed pump issue, attributing it to moisture damage during storage, with temporary replacements ordered. He also clarified the power line connection delays were due to detailed engineering and subcontractor ramp-up, but it's no longer on the critical path, with energization expected in late Q2 2026.
Ask follow-up questions
Fintool can predict
EGO's earnings beat/miss a week before the call


