Good morning and welcome to National Grid's full-year results presentation. I'm Angela Broad, Head of Investor Relations, and it's great to have so many of you on the call today. Please pay attention to the cautionary statement at the front of the pack. As usual, a Q&A with John and Andy will follow the presentation. Please join via the conference call to ask a question or use the tab at the bottom of the webcast to submit a written question. All of today's materials are available on our website. Of course, for any further queries after the call, please do feel free to reach out to me or one of the IR team. With that, I'd now like to hand you over to our CEO, John Pettigrew. John.
Speaker 0
Many thanks, Angela. Good morning, everyone. Thank you for joining us to discuss our full-year results. I hope to see many of you later today at our Building Our Energy Future event for a deep dive on major capital projects we're delivering across the U.K. and the northeast US. As ever, I'm here with Andy Agg, and once we've been through our respective presentations, we'll be happy to answer your questions. Last May, we announced a refined strategy focused on pure-play networks. We also set out a new five-year financial framework and our plans for GBP 60 billion of capital investment. This will drive asset growth around 10% per annum and underlying earnings per share growth of 6-8%, whilst maintaining a strong balance sheet and delivering an inflation-protected dividend.
Alongside this, we set out our comprehensive financing strategy, including our GBP 7 billion equity raise, providing clarity over our funding to at least 2031. In the first year of the five-year framework, we've accomplished a huge amount despite a turbulent economic and geopolitical environment. We've delivered record capital investment of GBP 9.8 billion, in line with our plan and 20% higher than last year. This reflects the scale of the activity across all of our regulated businesses, including significant progress within our asset portfolio, where all six of our wave one projects are now under construction. A step up in asset health and network reinforcement in electricity distribution, over 350 mi of gas mains replacement across Massachusetts and New York, and good progress with our SmartPath Connect project in US electricity transmission.
We've also secured the supply chain and delivery mechanisms for more than two-thirds of our GBP 60 billion of capital investment. For ASTI, this includes contracts for the delivery of 12 onshore and two offshore projects, while also making good progress on Eastern Green Link 3 and 4 and SeaLink. In New York, we've made further progress with our $4 billion upstate upgrade, awarding contracts for the first phase as well as the engineering works for phase two. The policy and regulatory agenda on both sides of the Atlantic has also continued to move forward, further enhancing visibility on our investment plan. In the U.K., the government published its Clean Power Action Plan in December, and Ofgem published its decision on connections reform last month, which embeds "Is it ready?" and "Is it needed?" criteria into the connections process.
This will deliver a rationalized queue of projects aligned with the Clean Power Action Plan and clarify the specific investments and locations required in the outer years of T3. New legislation on planning reforms was also introduced in March, which aims to reduce the time it takes to deliver infrastructure projects. Whilst these reforms will be more impactful in the 2030s, there are important measures in the bill that have the potential to further de-risk our ASTI projects. In the US, we refreshed all three of our New York rate plans and agreed new rates for our electricity distribution business in Massachusetts over the last year. Altogether, this means that we've now agreed over 70% of our US investment with regulators over our five-year frame.
We also expect to receive approval for our electricity sector modernization plan in Massachusetts, where we filed for up to $2 billion of capital investment over the next five years to help deliver the state's clean energy policy. The combination of these firm foundations of our resilient business model, which provides strong regulatory protections from macroeconomic uncertainty and no significant exposure to energy prices or merchant risk, means that we are very well positioned and hugely confident in our ability to deliver our GBP 60 billion investment program. We will have much more to share on capital delivery at our investor event this afternoon, where we will showcase the sheer scale of our electricity transmission projects and how we have transformed the way we are delivering them. Turning now to some of the key highlights for the year.
have delivered a strong performance with underlying operating profit increased 12% to GBP 5.4 billion at constant currency. This reflects robust operational performance as a result of increased regulated revenues and flat controllable costs achieved through our focus on agreeing the right regulatory frameworks and efficient delivery. Underlying earnings per share was slightly ahead of guidance at GBP 73.3 and up 2%, reflecting the impact of a higher share count following the rights issue. A record GBP 9.8 billion of capital investment helped to drive regulated asset growth of 10.5%. In accordance with our policy to grow the dividend in line with the U.K. CPIH, the board has declared a final dividend of GBP 30.88 per share. This takes the total dividend for the year to GBP 46.72, an increase of 3.21% on last year's rebase dividend. Moving next to reliability and safety.
Reliability has remained strong across our U.K. and U.S. networks despite severe weather events across our jurisdictions. An example of this is Storm Dara last December, a once-in-a-decade storm that hit our U.K. electricity distribution networks, causing significant damage across the Southwest, South Wales, and West Midlands. Our teams worked tirelessly around the clock, restoring power to 95% of customers within 48 hours. Last week, the NESO published its interim report investigating the outage following the fire at our North Hyde substation in March. We welcome the report, which establishes a timeline and sequence of events and outlines further steps required to deliver the final report in June. On safety, our lost time injury frequency rate was 0.1, in line with our group target.
As our workload increases, we continue to invest heavily in attracting, developing, and retaining a qualified and competent workforce with robust training programs built around a culture of safety. We have also set protocols for our contractors so that high safety standards are maintained right across the workforce. Turning to our operating performance across the group, starting with U.K. electricity transmission. Investment increased by 57% to GBP 3 billion, reflecting the ramp-up in the first wave of six ASTI projects, major substation upgrades, and a further 4 gigawatts of generation being connected to the network. This included the U.K.'s largest battery storage unit at Lakeside in North Yorkshire and a 1.2 gigawatt offshore wind farm in Dogger Bank. The business delivered a return on equity of 8.3%, outperforming its allowed return by 100 basis points.
Turning to regulatory developments, in December, we submitted our GBP 35 billion RIIO-T3 business plan, representing the most significant investment in the U.K.'s electricity transmission network in a generation. This ambitious plan will nearly double the power that can flow across the country, directly connecting 35 gigawatts of generation and 19 gigawatts of demand, and create optionality for a further 26 gigawatts, all whilst maintaining world-class levels of reliability. Our submission also included clear evidence of the need for an investable financial framework, including a real 6.3% allowed cost of equity, appropriate levels of cash generation, and incentive mechanisms that will deliver benefits to both networks and consumers. Under our proposals, we expect our investment plans to avoid constrained costs around GBP 12 billion over the price control period, offsetting the impact of investment to customer bills. In addition, we're also pleased to see Ofgem's decision on the advanced procurement mechanism.
This will provide funding for transmission owners to secure supply chain capacity, covering items like switchgear and transformers. This builds on the approach Ofgem adopted under the ASTI regime, and we plan to utilize the framework from the middle of this year. Finally, on policy developments, in addition to the connections reform I mentioned earlier, the government published its planning and infrastructure bill. The bill includes a number of proposals that are important to us, including giving certain projects the flexibility to choose the type of consenting regime used and providing opportunities to accelerate the consenting process. The bill also includes proposals intended to increase public acceptability of electricity transmission projects alongside guidance for wider community benefits. Moving to strategic infrastructure.
This will get a lot of focus this afternoon, but to summarize, we now have the Great Grid Partnership up and running, the HVDC framework agreement in place, the supply chain secured for all 12 onshore projects, all wave one projects under construction, and we have continued to build our internal capabilities, and the workforce now stands at over 1,000 employees. In the last year, we put the platform in place, and delivery is well underway. Carl and his team will provide a lot more detail on our progress later today. Turning to U.K. electricity distribution. Capital investment increased by 14% to GBP 1.4 billion, driven by increased spending on asset health, network reinforcement, and connecting nearly 600 megawatts of renewable generation.
The business achieved a return on equity of 7.9%, and whilst this reflects the benefit of our synergy savings program, it was heavily impacted by costs from Storm Dara, as well as lower-than-anticipated allowances from Ofgem's real price effects mechanism that have not matched what we were expecting when the price control was agreed. We are working hard to address the ongoing headwind and expect performance to improve over the remainder of the price control period. This year, we have also made good progress in developing our role as the distribution system operator, or DSO, including our leading role in the development of flexibility markets. We now operate the largest market across all DSOs, allowing us to avoid over 200 gigawatt hours of renewable generation curtailment, lowering costs for consumers.
On the regulatory front, Ofgem published the ED3 framework decision at the end of April, which gives us an early indication of their thinking on the next price control period and is the starting point for the development of the sector-specific methodology. As I mentioned earlier, we were pleased to see Ofgem's decision on connections reform. Electricity distribution has been playing a leading role in driving forward these reforms, and over the last year, we've been able to implement the industry's technical limits initiative, accelerating the connection office dates on around 3 gigawatts of distributed generation and removed over 4 gigawatts of capacity from connections queues. Turning to the US, our investment in New York increased by 24% to GBP 3.3 billion.
This reflects a further 218 mi of gas mains replacement and a continued ramp-up in our $4 billion upstate upgrade program, including the reinforcement and upgrade works as part of CLCPA phase one and continued strong progress on SmartPath Connect, where we're rebuilding over 100 mi of transmission lines to connect large-scale renewable generation. Again, we'll have much more to say on our upstate upgrade program this afternoon. We achieved a return on equity of 8.7%, 94% of allowed, and 20 basis points higher than the prior year, reflecting strong performance in our downstate gas businesses in the first year of our new rate plans.
On the regulatory front, we reached a joint proposal in April on new rates for Niagara Mohawk business, which includes an improved return on equity of 9.5%, increased CapEx of around 50% over the three years, reflecting our step-up in electricity transmission investment and funding to modernize our electric and gas networks and support New York's clean energy goals. The joint proposal also includes provisions to mitigate bill impacts for customers by spreading increases over the three years of the plan and putting in place assistance programs for low-income households. In New England, capital investment increased by 5% to GBP 1.8 billion, reflecting continued gas mains replacement and increased asset condition and grid modernization work across our electric network. Our achieved return on equity was 9.1%, 92% of allowed, benefiting from six months of the new rate agreements in our Massachusetts electric business.
We've also seen a greater focus on affordability in the state, following increased bills from a colder winter. To assist Massachusetts gas customers, we agreed with the regulator to reduce winter gas bills by 10% during March and April, with a deferral to be recovered over the summer. On the regulatory front, in September, the DPU issued its rate case order for our Massachusetts electric business, approving a five-year plan with an allowed return of 9.35%. The order includes a new regulatory recovery mechanism that provides timely funding for growing capital investment, an updated performance-based rate mechanism providing inflation protection for operating and maintenance costs, and increased allowances to cover the increasing cost of storms. Taken together, these enhanced recovery mechanisms are helping us to earn closer to the allowed return.
As I mentioned earlier, the DPU has also approved our electricity sector modernization plan for anticipatory investments to support the decarbonization of our networks. From a policy perspective, last month, we submitted our climate compliance plan, setting up a strategy to enable our Massachusetts gas network to advance state decarbonization goals whilst maintaining safe, reliable, and cost-effective service for our customers. Finally, last November, Governor Maura Healey approved legislation that reforms the permitting process for utility infrastructure. This new approach sets maximum time frames for approvals for capital projects in the state. Finally, in National Grid Ventures, capital investment was 43% lower at GBP 378 million, following completion of the Viking Link to Denmark last year.
During the year, we've seen good operational performance across the National Grid Ventures portfolio, including good availability from our interconnector fleet, high levels of availability and utilization at our Long Island generation business, and at our Grain LNG terminal, where we're making good progress on the construction of the new tank. On the regulatory front, last month, Ofgem published their decision on the regulatory framework for offshore hybrid assets, an important next step as we continue to develop our Line Link project as a next-generation interconnector. As I said at the start, we've achieved significant progress across all areas of the business in the last year as we continue to efficiently deliver safe, secure, and clean networks for the future. Let me stop there and hand over to Andy to walk you through the numbers before I come back and talk about priorities for the coming year. Andy.
Thank you, John. Good morning, everyone. I'd like to highlight that, as usual, we're presenting our results on an underlying basis and at constant currency. I want to start by expanding on what John has said about National Grid's financial resilience. The visibility that our business model provides and the stability it gives is unwavering, however volatile the macro environment, including times such as now. A large part of that can be attributed to our regulatory frameworks, but it is also a consequence of our efficient delivery, with controllable costs broadly flat this year and our robust procurement and financing strategies. Together, these enable us to manage the impacts of inflation and cost pressures, changing interest rates and fluctuations in exchange rates, and importantly, that enables us to deliver stable and predictable growth through our significant capital program.
Many of you will also know that we have substantial inflation and cost protections, particularly in our U.K. regulated businesses with indexation of our regulated asset base. In the U.S., around 90% of our supply chain is domestically sourced, and even if higher costs do come through, we can manage this through alternative suppliers or the pace of discretionary spend, with any additional spend ultimately being picked up in the following rate case. We are also positioned so that the impact of exchange rate volatility from our U.S. businesses is limited. We consistently hedge around 70% of our U.S. gross assets with dollar-denominated debt. This means, from an earnings perspective, our general rule of thumb is that for every $0.05 move in the average U.S. dollar to sterling exchange rate, we only expect to see a £0.01 impact on EPS on an annualized basis.
Finally, from a financing perspective, our regulated operating businesses broadly match leverage to our regulatory frameworks, which enables us to efficiently recover debt costs. We also hold around 30% of our debt book at the whole code level, with maturities out to the 2030s, and any higher expected interest costs refinancing have been factored into our five-year financial frame. We have also set out our comprehensive financing plan, which sees us fully funded until at least the end of RIIO-T3. As I say, all of these things add up to create a very stable platform from which to operate and deliver on our plans. Now, let me take you through our financial performance. I'm pleased to be reporting a strong start to our five-year plan. Underlying operating profits on a continuing basis increased by GBP 589 million to GBP 5.4 billion, up 12% on the prior year.
This was mainly driven by strong performance across our regulated businesses, including higher revenues and strong cost efficiency, partly offset by expected lower revenues from our interconnectors. Higher operating profit combined with lower finance costs has led to an underlying earnings per share increase of 2% to GBP 0.733 per share, slightly above guidance and including the impact of a higher share count following the rights issue. Group return on equity was 9%, supported by the growth in our regulated earnings offset by a high denominator reflecting the rights issue. In line with our policy, the board has recommended a final dividend of GBP 0.3088, taking the full-year dividend to GBP 0.4672 per share, representing a 3.2% increase compared to the prior year rebase dividend and in line with average CPIH inflation.
As John said, we have continued to deliver record levels of investment, with capital investment from continuing operations increasing 20% to GBP 9.85 billion, helping drive regulated asset growth of 10.5%. Now, turning to our business segments. Starting with U.K. electricity transmission, where underlying operating profit was GBP 1.4 billion, 9% higher than last year. This was helped by increased totex allowances, indexation, and higher allowed returns, partly offset by increased depreciation reflecting growth in the asset base. Capital investment of GBP 3 billion was up 57% versus the prior year. This included the ramp-up of our wave one ASTI project spend, including Eastern Green Link 1 and 2, as well as the four onshore projects and construction activities on new customer connections, partly offset by lower spend on London Power Tunnels 2 and the Hinkley connection.
We've achieved an 8.3% return on equity, delivering outperformance of 100 basis points, and we remain on track to achieve 100 basis points of average annual outperformance throughout RIIO-T2. We also saw underlying operating profit of GBP 115 million from our electricity system operator over the first half of the year prior to its sale to the U.K. government. Moving to U.K. electricity distribution, underlying operating profit was GBP 1.2 billion, GBP 51 million higher than the prior year, reflecting an increase in revenues from indexation, partly offset by high depreciation and one-off costs and incentive revenue impacts following the severity of Storm Dara. Capital investment was GBP 1.4 billion, 14% higher than last year, with increased investment in asset replacement and reinforcement work.
We are on track to deliver our GBP 100 million group synergies target by 2026, having achieved GBP 88 million as of the end of this year from areas such as procurement and operations. We achieved an ROE of 7.9% in the year, outperforming our allowance by 20 basis points, which is lower than our aim to achieve 100-125 basis points of outperformance. This reflects the one-off impacts from Storm Dara and an impact arising from the real price effects, or RPE mechanism, where lower than anticipated allowances due to reductions in commodity indices since the start of the RIIO-ED2 period have not tracked actual costs incurred. We are working hard to mitigate this headwind and expect to improve in-year outperformance towards 100 basis points by the end of ED2.
Moving now to the US, our New York business achieved an 8.7% return on equity, 94% of its allowance, and 20 basis points higher than last year. Underlying operating profit was GBP 1.45 billion, 43% higher than the prior year. This reflects rate increases in our downstate gas businesses and cost efficiencies, enabling us to deliver broadly flat controllable costs, partly offset by high depreciation on our increased asset base. Capital investment was GBP 3.3 billion, 24% up on the prior year. This was driven by higher electric investment, including our Upstate Upgrade projects with SmartPath Connect on track to energize in December 2025, as well as high gas investment driven by a further ramp-up in gas mains replacement and our updated downstate rate cases. In New England, the return on equity was 9.1%, 92% of its allowance.
This was 10 basis points lower than the prior year and 40 basis points higher after adjusting for a one-off property tax recovery last year. Underlying operating profit was GBP 924 million, up 15%. This was driven by higher rates in our gas and electricity businesses, including through our new capital tracker and delivery of cost efficiencies, partly offset by high depreciation and other costs. Capital investment was GBP 1.75 billion, 5% higher, driven by higher electric investment for increased asset health and maintenance work and the advanced metering infrastructure rollout. We also continued to invest in our gas networks, including the replacement of 135 mi of gas mains this year. Moving to National Grid Ventures, underlying operating profit, including joint ventures, was GBP 455 million, 116 million lower than the prior year.
Higher profitability from a full year of Viking operations was more than offset by expected lower revenues on IFA II and the North Sea Link. Capital investment was GBP 378 million, down 43%, reflecting the commissioning of our Viking Link interconnector last year and the classification under IFRS of National Grid Renewables and Grain LNG as held for sale from the end of September, which means investments into these businesses are excluded from reported group capital investment. During the year, our community offshore wind joint venture paused development activity in line with the broader slowdown of the US offshore wind industry. Whilst there are longer-term trends that give us confidence in the need for offshore wind generation in the Northeast, significant nearer-term policy uncertainty has led us to recognize an accounting impairment as an exceptional charge.
We recorded an operating loss for other activities of GBP 143 million, including adverse fair value movements in the National Grid Partners portfolio. Net finance costs were GBP 1.36 billion, GBP 116 million lower than the prior year, with the benefits of lower net debt following the rights issue and lower inflation on index-linked debt, partly offset by the impact of higher refinancing costs, where we have issued GBP 3.2 billion during the year. For the full year, the underlying effective tax rate, excluding the share of joint ventures, was 15.4%, 20 basis points lower than the prior year. This reflects higher levels of capital expenditure qualifying for full expensing compared to last year. Underlying earnings were GBP 3.5 billion, with EPS at GBP 73.3, up 2% on the prior year. Moving now to cash flow. Cash generated from continuing operations was GBP 7 billion, down 4% compared to the prior year.
This decrease was driven by timing as we returned balancing charges within the ESO in the first half of the year, following over-recoveries in the prior year. Net cash inflow at GBP 954 million was GBP 4.6 billion higher than the prior year, reflecting the proceeds of our rights issue, partly offset by the increase in capital investment. Combined with disposal proceeds from the ESO and the remaining 20% stake in gas transmission, we saw a reduction in net debt of GBP 1.7 billion to GBP 41.4 billion. Moving to our FY2026 guidance, which is presented at an assumed exchange rate of $1.3 to sterling. EPS growth is expected to be at the lower end of the 6-8% range, reflecting the headwind of a slightly weaker dollar. Capital investment is expected to be over GBP 11 billion next year, driving asset growth of around 11%.
Net debt is expected to increase by just over GBP 6 billion, excluding expected proceeds from the National Grid Renewables and Grain LNG sales. As usual, detailed business unit guidance has been provided in our results statement. Turning to the five-year framework, as I said at the beginning, as a result of our visibility and resilience, we are reconfirming our financial framework from April 2024 to March 2029. We still expect to invest around GBP 60 billion over five years, driving asset growth of around 10% and EPS growth of 6-8% from this year's baseline of GBP 73.3. Our aim remains to grow the dividend in line with average CPIH, and we remain committed to maintaining our current investment-grade credit rating. With that, I'll hand you back to John. Many thanks, Andy.
Before we move to your questions, I want to spend just a few minutes setting out National Grid's priorities for the coming year and the journey we're on to support economic development, energy security, and decarbonisation across our jurisdictions. Starting in the U.S., where nearly half of our investment will be spent over the five-year frame. From a regulatory perspective, we have a number of key priorities. In New York, having reached a joint proposal for our Niagara Mohawk business, we'll continue to engage with the PSC ahead of the anticipated approval by the Commission in the summer. In Massachusetts, we'll continue to work with the DPU to agree the recovery mechanisms under the Electric Sector Modernisation Plan. We'll also be preparing our next rate filing for Massachusetts Gas, and we'll work with the DPU to put forward a plan that balances investment needs and customer affordability.
On policy, we'll continue to work closely on its state energy plan to develop a comprehensive roadmap to a clean, resilient, and affordable future for our customers. In Massachusetts, having filed our Climate Compliance Plan last month, we'll be supporting the discovery phase over the coming months and will work with the states as they advance the energy affordability bill. Across our US businesses, we're supporting our policymakers to understand the impacts and opportunities of increasing demand growth from data centers, and we're supporting federal policymakers as they begin to look at resource adequacy in the region. Moving to the U.K., in electricity transmission, our priority will be to continue to ramp up capital delivery, including commissioning two further circuits of our London Power Tunnels project.
Our primary regulatory focus for the year is to reach agreement with Ofgem on an investable RIIO-T3 framework that will allow us to deliver at the unprecedented scale and pace that is needed to meet the U.K.'s ambitious climate goals. We expect Ofgem's draft determination to be published in June, with a final determination in December ahead of a new regulatory period starting in April 2026. We'll also be focused on supporting the NESO with the recontracting of the connections queue, which in turn will clarify the specific investments and locations required in the outer years of T3. Staying on the topic of connections, we're also seeing significant increases in data centre requests with 15 gigawatts of signed contracts now in our pipeline. Our RIIO-T3 plan has been developed to meet this demand and we're also supporting the government's recently formed AI Energy Council.
Here, we're working to meet the challenges of increased power demand, including proposals for AI growth zones dedicated to data centre development. On the policy front, we expect to see the planning legislation progress through Parliament and will continue to advocate for wider planning reforms. Through our input into the NISA, we'll support progress on the longer-term Strategic Spatial Energy Plan, which should align with the government's forthcoming industrial strategy. We want to see a skills strategy developed, which together with industry creates a collective view of the workforce needed for 2030 and beyond. In strategic infrastructure, our priority is to continue to ramp up the ASTI program, where we'll be focused on stepping up work on the six Wave One projects that are now under construction and finalizing the procurement contracts for the remaining offshore projects.
Once complete, we will have secured T1 supplier contractors for all 17 of our ASTI projects. We will also be focused on the consenting process with a total of eight consultations planned this year. In our electricity distribution business, our priority is to complete our targeted GBP 100 million synergy benefits and deliver improved returns. Following the publication of the ED3 framework decision document, we look forward to engaging in the sector-specific methodology consultation later in the year. Turning finally to National Grid Ventures, our priorities will be to complete the sale of National Grid Renewables, agree the sale of Grain LNG, having launched the process at the end of April, and to continue the development of our Lion Link project in the U.K. and the Propel transmission project through our New York Transco joint venture. In summary, it has been another year of enormous progress.
As you'll have seen, I've recently announced my decision to retire from National Grid, and I'm delighted that the board has appointed Zoe Yonovich as my successor. She has all the attributes required to deliver on the significant growth opportunity ahead. I'm looking forward to welcoming Zoe in the autumn and working with her before handing over the reins in November. It's been an immense honor for me to work with so many talented people over the years and to lead the company I joined as a graduate. I'm very proud that National Grid is leading the way to a new energy era, building the next generation of networks to unleash the energy needed to meet increasing demand. We're delivering extraordinary change at National Grid, implementing the largest ever overhaul of our networks across all the jurisdictions that we serve.
In a turbulent and unpredictable world, National Grid is a beacon of stability with an investment proposition that provides high asset growth, strong earnings growth, and an inflation-protected dividend. In this context, we remain focused on delivering secure, affordable, and clean energy for our customers and communities whilst providing long-term value and returns for our shareholders. As you've heard, there is much to do in the coming months, and I remain fully focused on ensuring we don't miss a beat so that I leave National Grid in the strongest possible position for its future success. Let me stop there and give you the opportunity to ask questions. Okay, there are lots of questions coming through, so I'm going to start with Dominic from Barclays, and then after that, I'll go to Sarah at Morgan Stanley. Dominic, would you like to ask your question? Hi there. Yes, thank you.
It's Dominic Ash from Barclays. Thanks for your presentation, and also I'd just like to say thank you, appreciate your time at Grid, and wish all you the best in your decision on moving on. A couple of questions from me, please. Firstly, on RIIO-T3, we clearly have the DD date now in the diary for the 25th of June. You submitted your business plans in December with, I think, a GBP 35 billion top tax program, and since then, clearly, there's been a few movements in U.K. policy and a few sort of projects sort of falling out and going sort of left and right. On your conversations that you've had with Ofgem, what do you expect to see different in the DD to sort of your business plan with regards to CapEx to the real nominal split in the debt calculation and on the returns?
I think Ofgem was 5.5% real, and I think you requested 6.3%. The second question is just sort of following up from that. Is that the Iberian blackout a couple of weeks ago, what sort of discussions have you had with policymakers and with the U.K. sort of regulators on kind of what happened, what the impact here, and what sort of opportunities or changes are potentially needed in the U.K. to ensure that something like that does not happen here? Thank you. Okay, thanks, Dominic. There is quite a lot in that. Why do I not start on RIIO-T3? I will ask Andy to talk about nominal debt, and then I will come back on the Spain blackout. I mean, as you said, we made the business plan submission in December, and I would say since then we have had really productive conversations with Ofgem.
As you expect, we're in the sort of last few months of the RIIO-T3 process that has been going for two and a half years, I think. What I'd say is our focus at the moment is very much on the financial framework. You might be aware we had a roundtable with our investors and Ofgem recently, and I'd like to thank our investors who attended that, who directly reinforced the message that we've been giving Ofgem around the importance of an investable framework for RIIO-T3. Our focus continues to be as it was when we made the submission in December. There are three elements to the financial framework. The first is the returns. We've been very clear that we believe that in the range that Ofgem set out, the base return should be at the top end.
In our submission, we talked about 6.3 being an appropriate level. Also, on top of that, the cash characteristics need to be right to get the right balance of earnings growth and asset growth, and also that the incentives are there as well to get to a sensible return that is comparable to what we see internationally. All of those conversations are going on, as you would expect. In terms of the investment levels, in terms of ASTI, which is a big part of the electricity transmission, we do not see the recent announcements impacting that investment profile. The GBP 35 billion that we submitted is consistent with everything that we talked about with regards to ASTI and the GBP 60 billion. Electricity transmission makes up about 23 of the 60 in different time frames, but that 23 is consistent with the 35 we submitted in the business plan.
Andy, do you want to just talk about nominal debt? Yes, and thanks, Dominic. Yeah, I think Ofgem were fairly clear in their SSMD about signalling the direction of travel on moving to a sort of a nominal debt approach. We've seen nothing since then that would indicate that's less likely than it was. Obviously, we'll have to wait and see what comes out on the 25th of June, but everything we're seeing at the moment is that remains the most likely direction of travel. I think, as John said, for us, that's one element of ensuring that the total package gives us the right balance and including cash characteristics overall. Clearly, a move to a nominal debt does serve to accelerate some level of cash, but it's only a portion of, I think, of the overall level that we've asked for in our business plan.
Yes, that's what we'll be looking for on the 25th. In terms of the incident in Spain, Dominic, I mean, I think we're all waiting to see what comes out of the investigation. As far as I'm aware, there is no clarity yet on the root cause. Lots of speculation and lots of hypotheses. I mean, I do think it is massively important that given the increasing dependency society has on electricity, not just for lighting, but for heat and transport going forward, that actually things like resilience are looked at very carefully. I can talk about the U.K. in terms of I've seen some of the hypotheses around renewables.
When the National Energy System Operator was part of National Grid as the electricity system operator, we started several years ago looking at pathway products, as we call them, which are effectively technical products that would be needed to support a renewable system for things like frequency response from different sources, voltage control, reactive power, and inertia. I know the National Energy System Operator holds a certain level of inertia on the system depending on how many renewables are there. That standard is in place in the U.K. The reality is we need to wait to see what comes out of the investigation, what the root cause is, and then from that, we will be able to learn any lessons that are relevant for the U.K. Thank you.
Okay, so I was going to go to Sarah next from Morgan Stanley, and then after that, I'll go to Pavan at JP Morgan. Sarah, would you like to ask your question? Yes, thank you very much. First and foremost, John, congratulations for all you've achieved during your time at Grid. I've got two questions, please. The first one, it's slightly different, but similar vein to John's second question. Mine's specifically related to NESO's final recommendations and conclusion report on the North Hyde substation fire that we're expecting by the end of June that you mentioned. Just wondering what you expect to see in that that's tangible for the direction of investment needs or maybe put differently, what would you like to see in that final report? Then secondly, a high-level question, please.
Given the upcoming CEO succession, I feel like it's very much obligatory to ask a reflective question. John, I'm curious, how would you pitch the National Grid equity story today versus how you would have pitched it on day one in a CEO seat? Thank you. Thank you, Sarah. You've made me laugh this morning, if nothing else. Look, let me talk about the North Hyde incident. First of all, as you can imagine, we were pleased to see the interim report that came out from NESA last week. I think it was really sensible to set out the time frame, the sequence, and the next steps as an initial sort of part of the report. We are working closely with NESA. We're providing all the information that you can imagine that is needed for that type of investigation.
I'm hopeful that the report that comes out in June will cover all aspects of the incident. As you know, from our perspective, it was a very rare event. In my very long career, I can't remember a circumstance where we've had such a ferocious fire that's taken out the substation. Power was also available into the local area, into the Heathrow, right through that, through two other substations. I'm hoping it will look at the specifics of the acid failure at the substation. It will look at broader resilience issues. It will look at the interaction between transmission distribution and national critical infrastructure. It will look more broadly around the changing nature of networks as they go forward. From the scope of the terms of reference I've seen, I think it will cover all those aspects.
We will look forward to seeing the report when it comes out at the end of June. In terms of, I did not quite get the question, but in terms of, as I move on from National Grid, the proposition that National Grid makes today to its equity investors is very clear. It is very much a growth and dividend proposition. As you know, we have set out for the next five years that we are looking to grow the asset base by 10%, and we are looking to grow the dividend, our policy is to grow it in line with CPIH. That very much is the focus for National Grid. I think from where I started back in 2016, growth was significantly lower back then. We were more typical, perhaps, of what people expect in a utility. As we look forward, growth is an important part of the proposition.
That is all underpinned, I think, by the fact that, as we said in our results today, what National Grid is, it's very predictable, it's very stable, and has an incredibly resilient business model in a world in which there's quite a lot of turbulence. That proposition of growth and yield, but also stability and predictability, I think, is the key to an equity proposition for our investors. Perfect. Thank you. Thanks, Sarah. Okay, we have Pavan, and then after that, we'll go to Mark at UBS. Hi, team. Good morning. Thank you for taking my questions. John, I'd like to echo Dom and Sarah's congratulations on your career at National Grid. My two questions are, firstly, you mentioned, John, in your speech, some of the measures you're taking on affordability in Massachusetts.
I guess, if you can go into a bit more detail on what you're seeing on affordability pressure in the US, any pressure you're seeing on returns, and how your conversations are going with the US regulators and with US policymakers on this topic. My second question is on the planning and infrastructure bill. I appreciate it may not have on your five-year frame, and I think you say this in your statement, but are there any, can you talk about any positives that could be there in the five-year frame or certainly beyond that, how we should think about that affecting National Grid, please? Thank you. Yeah, thanks, Pavan.
I mean, in terms of affordability, I mean, I think you're aware that National Grid thinks very carefully and thoughtfully around any rate case that we're doing to make sure we get the balance right between the investment that many of our regulators and policymakers want us to make and ultimately affordability. Therefore, we have lots of deep conversations with our regulators to make sure that any submission reflects that. In New York, you'll have seen that in terms of if I take our latest rate case in NIMO, we've got a joint proposal which is for three years. Within that, we've actually smoothed out the increase in the bills over that three-year period to reflect the fact that commodity prices have been quite high in the US during the winter, and therefore, that's mitigated the impact for customers whilst doing the investment we need.
We also set aside about $290 million to support vulnerable customers over that rate case period, with nearly $100 million in the first year. That is us working closely with the regulators to make sure we have got that balance right. In terms of returns, then in New York, as you saw in the joint proposal, we have got a joint proposal that increases our returns, I think, reflecting the nature of the investments that we are doing from 9% to 9.5% for Niagara Mohawk. Similarly, in Downstate New York, you would have seen the three-year rate case there where we saw an increase to 9.35%. I think the regulators are thoughtful in making sure that it is an investable proposition as we do this significant investment, but we are careful as we think about affordability.
In Massachusetts, you would have seen, as a reference in my speech, high commodity prices during the winter meant our gas customers were struggling a bit. We were very happy to work with the regulator to provide a 10% discount on bills in March and April, which we will then recover in the summer when commodity prices are low. As we look forward, again, we will be very thoughtful both in terms of how do we deliver the investment needed in our rate case for Massachusetts gas, and how do we reflect that in affordability. You may have seen this week, actually, that the governor of Massachusetts has launched an initial affordability bill.
It's a 120-page document, and we will work through that with the governor's office and the PSC to see how we can support and contribute towards that as it goes through the sort of various machinations of committees and the Senate and Congress and so on. That's sort of how we think about affordability, but it's an important issue, and you're quite right to raise it. In terms of billing and infrastructure, the planning and infrastructure bill, I mean, a lot of what's in that bill are things that National Grid has been advocating for. We're really pleased that the government is moving forward with that. There's a lot in there that will streamline the planning process and make it more effective and shorter. There is some legislation in there to make the ability to challenge more focused.
Of course, there's proposals for things like community benefits. There's also been a recent amendment, actually, to shorten the statutory consultation process that, again, could potentially take about a year out of the planning process in the U.K. We are very supportive of all of that. In my speech, I referenced the fact that it will help to de-risk, I think, some of the ASTI projects, and some of the legislation will absolutely do that. Most of the ASTI projects were already in train. As you've heard, our six projects that are phase one already have planning and are in construction. We've got eight consultations running this year. By the time the legislation goes through, we would have been through the majority of our ASTI projects in terms of the planning process.
I think it really helps us as we move into the 2030s and beyond. Thank you. Okay. Thanks, Pavan. I'll go to Mark next, and then Ahmed from Jefferies. Mark, would you like to ask your questions? Hey, John, no. Firstly, congratulations on the shareholder returns you've generated over the last nine or ten years. Looking forward to seeing where you move on to once you retire from National Grid. I have two questions, one for you, John, one for Andy. John, EGL1, which you haven't mentioned, is 16 months late, very early on in the project. It's a GBP 2.5 billion project. I think Ofgem's minded, from their wording in their document, they're clearly minded to give you and your partners a penalty for that.
Given you speak a lot about the framework agreements and booking out the supply chain, but the supply chain is struggling. So how can we be sure that we're not going to see other further delays like this, 16 months delayed to EGL1? My second question for Andy is just on community wind. When we spoke previously, my understanding was National Grid has certain protections to put the project back to your partners, RWE. You've written off what would seem most, if not all of it, today. Is there any chance of you recovering some of the cash somehow from that, or is that GBP 300 million completely a sunk cost and now an impaired cost? Thank you. Thanks, Mark. And thanks for your comments as well. I mean, in terms of EGL1, I don't think you should infer anything about the other ASTI projects when you look at EGL1.
EG1 actually has quite a long history, and a lot of it was developed under the LOTI process rather than the ASTI process and all the regulatory frameworks that we put in place around that. Having said that, at the point at which we were asked to take the project forward because there was a debate about whether it was going to be part of competition or not, we immediately went out to the market to see what was available in the supply chain. The reaction from the supply chain was they could support it, but in a slightly different time frame. You have seen the consultation for Ofgem, in which they have said that they are not minded to give us the extension. One of the things they say in the consultation is that they do not feel that we have provided sufficient evidence on what the worldwide supply chain looks like.
That consultation is still live. As you can imagine, we are going back to Ofgem. We believe we have significant evidence to demonstrate that actually there was a limitation in terms of the time scales that that supply chain could deliver at the point at which we were asked to take that project forward. For the other ASTI projects, as you know, we've got an awful lot of things in place, including advanced procurement mechanisms and also licensability associated with the supply chain. I don't think you should read anything across from EG1 for the other projects. We'll talk a lot more about this this afternoon at our event. Our focus at the moment is providing that data to Ofgem and the evidence to Ofgem that they require to get them comfortable that actually making a move in the date is an appropriate thing to do. Andy.
Yeah. Morning, Mark. Thanks for the question. I guess just to remind you what I said in the presentation this morning, we've worked very closely and continue to work very closely with our partner, RWE, on both the short-term decisions around the pause in our development activity on Community Offshore Wind, but also continue to be alive to how that may evolve in the future and very much looking to continue to see options to take forward that commercial opportunity. What we've announced this morning is very much an accounting impairment. Given the short-term uncertainty created by some of the recent pronouncements and other activities in the Northeast, from an accounting perspective, we believe it's appropriate to impair the value. To your question, we've fully impaired our investment down to zero with the GBP 303 million that we've disclosed this morning.
As I said, and John said in his remarks, I think we continue to view that there are likely further energy needs in the northeast. To the extent that means this project comes back on, we will be very close working with RWE to pursue that. In terms of the protective rights, I think we have always said that, yes, we do have them, but they are attached to particular milestones through the course of the project. Of course, that will therefore be dependent on whether those projects go ahead as to whether those rights come into play. Okay. Thank you very much, Mr. Wynter. Thank you, Mark. I will go to Ahmed now at Jefferies and then perhaps Deeper at Bernstein. Ahmed. Yes. Thank you, John. Firstly, again, best wishes from my side as well. I have three questions.
Actually, just coming back to the comments you made about affordability in the New York region, I saw some press commentary from the New York governor yesterday, which talks about the affordability and how sort of the bill rises sort of coming through from rate reviews. That is obviously sort of coming despite sort of the measures that you have highlighted. How should we think about, particularly around the NIMO process from here? Is there something more to be done? Could the process be longer from here, or does this need to be better engagement between the stakeholders on what is actually sort of getting implemented? That is my first question.
My second question is I would be interested in your perspective on the other sort of big debate of zonal pricing in the U.K., particularly if you think that could play a big role in defining transmission investments into the 2030 period in the U.K. Finally, one for sort of any, the guidance for this year seems to be ahead of where consensus expectations are. Is there anything specifically you will call out where you sort of see the outlook better versus consensus? Thank you. Thanks, Ahmed. I mean, in terms of, I'll start with affordability and then zonal, then I'll need to talk about guidance. In terms of the affordability, I mean, I'll just reiterate, I think, what I've said, which is we worked very closely, not just with the PSC, but with the governor's office to make sure we get the balance right.
I was pleased that the joint proposal that we put forward was one that enabled us to be able to make those investments. It is about $5.5 billion across the three years, both electricity and gas, but with a single-digit increase in bills. We did not see any intervention from the governor in the same way as that has happened with other utilities, to be blunt. I think we have tried to get the balance right, recognizing what is going on in New York. As I said, there is quite a major investment in supporting vulnerability with the $290 million as well, which has been supported by PSC staff. I think we are in a reasonable shape, but we are very conscious around that. In terms of zonal pricing, look, I mean, we spend a lot of time thinking about zonal pricing. It does not immediately impact on National Grid, to be honest.
People are talking about implementation because it's incredibly complex over a sort of five-year period. It is something for the early 2030s. It is not going to impact on our GBP 60 billion capital investment program. Lots of debate in the industry, as everybody's aware. I mean, we can see that there are potential advantages for zonal pricing in terms of things like price discovery, locational signals, and resolution of operational constraints. At the same time, we can also see there's just a huge amount going on in the industry at the moment with retail reform, connections reform, the rollout of smart meters, the scale of investment right across the industry that requires a degree of stability and certainty so that people are comfortable with that. I think the bar for any incremental change on top of what's already going on should be very, very high.
My sense at the moment is that now is probably not the right time for introducing a major reconstruction of how the market operates through zonal pricing and that in the 2030s, the networks will look very different. I think maybe that is the time when you might potentially look at the advantages of zonal pricing. To do it today, it just does not feel like the right time. Andy. Yes. Morning, Ahmed. Thanks for the question. As you will be aware, this is the first time we are giving formal in-year guidance for FY2026. Previously, we have obviously given our five-year frame where we have guided to the 6-8% CAGR over the five years. I think previously we said that there was no reason we would not expect sort of things to be relatively linear. No real surprises for us.
As you see, we've guided to be within the 6-8% range next year or in FY2026, albeit towards the lower end with the impact of the dollar move. That will continue to come from investment-driven growth in our businesses and obviously some of the new rate cases coming in in the US, as John's mentioned as well. Continued asset growth in the UK and asset and rate case growth coming from our US businesses. Thank you. Thanks, Ahmed. Let me go to Deeper at Bernstein. After Deeper, I'll go to Martin at Bank of America. Deeper. Thank you so much. Congratulations, John. Thank you so much for your leadership. The two questions that I had, one was on EV underperformance. You're now guiding that the outperformance is lower. Obviously, this year, you had the storm impact.
Could you walk through what exactly is the cost item that's deviating on the RPEs? Is there any sort of read across to RIIO-T3? Could something similar kind of crop up there? What mechanisms will you use for that? My second question is on your RIIO-T3 plan. Out of the GBP 35 billion of targets, roughly GBP 9 billion or so is unconfirmed sort of projects. I was just wondering, given everything else you've been seeing with the connections just for and 2030 clean plan, do you expect a substantial chunk of that GBP 9 billion to also get implemented during RIIO-T3? I do recognize that your five-year frame and the T3 frame is off by a couple of years, right? Where would you see that GBP 35 billion realistically being delivered in RIIO-T3? Thank you. Okay. Sure. Yeah. Morning, Deeper. Thanks for the question. Yes.
As we said this morning, I think we've seen two headwinds flowing through the electricity distribution ROE for the year. One was due to Storm Dara, where we've seen pretty much unprecedented, certainly in recent memory, severity of the storm's impact. That has flowed through both in terms of direct costs, but also in terms of how it impacts the incentive, the customer incentive performance and connections incentives. That is about half of the impact. The other half has come through from the RPEs. The issue there, again, as I said in my presentation, is the way the indices are set up within ED2 means that effectively they are more generic indices. What they have done is the performance of those indices has not really tracked the cost experience that we've seen. I think we view this as a sector-wide issue.
If you look across some of the other DNOs, and it is definitely something that we would look to take forward into the conversations with Ofgem around ED3, obviously very early stages there. We will continue to look to offset that. You've seen in our guidance that we're guiding towards 50 basis points of outperformance next year and growing towards 100 by the end of ED2. In terms of your question around, is there a read across to transmission? No. Everything we've seen, the way the indices are set up in transmission is they much better relate to the types of spends that we have. And the indices there are demonstrating that the RPE mechanism is doing its job and making sure that there is sort of protection in the way allowances shift within the transmission business.
In terms of RIIO-T3, Deeper, I mean, I'd say that I think I said in my speech that of the GBP 60 billion, GBP 23 billion is ET, and we still believe that is our best view of what it's going to look like between now and 2029. Beyond that, we're still comfortable with the GBP 35 billion that we set out in the RIIO-T3 business plan. I think one of the key things over the next 12 months that will give us a little bit more solidity at the back end of RIIO-T3 is the connections reform process. As you know, Ofgem have now made the decision on connections reform, moving from a first-come, first-served to a first-ready and needed for CP2030. Over the course of this year, NESO and the electricity transmission companies, including National Grid, have to now reorder the queue.
It will be done in sort of chronological order, starting with 2027, 2028, 2029, 2030. That needs to be done by December of this year. I think that will help to give us a better indication of the makeup of the RIIO-T3 plan. As you recall, the way it was submitted to Ofgem was in two parts. There was GBP 11 billion that was absolutely certain, and then GBP 24 billion that required some work to be done on it. At the moment, we're still comfortable with that. I think the connections reform process will give us a bit more solidity at the back end, and we'll be able to update once we've done that. With that, I'm going to move to Martin, which I think is the last question that we have. Martin, over to you. Yes. Thank you for taking my questions.
Congratulations on a very distinguished career with National Grid. My first question is related to the risk of higher tariffs in the US. You mentioned that 95% of the supply chain is domestic. Could you give us some examples? What is included in that 5% that is not domestic? What actions have you taken or could be taking to mitigate any potential risks that could occur? My second question is actually related to the guidance you have provided for the current financial year. You are guiding for net financial expenses to be only increasing by $40 million, I believe, whereas you expect net debt to increase by as much as $6 billion. Why such a limited increase in financial expenses despite significantly higher net debt? Thank you. Okay. Thanks, Martin. I'll take the first, and then I'll only take the guidance question.
I mean, in terms of high tariffs, just to reiterate, we do not see it having a significant impact, partly because more than 90% of the products and services that we source in the US are domestic. Maybe just go down a level. We do have supply chain for things like pull-up transformers in Mexico, and we do import some steel from other countries, including India and Canada. We have the opportunity, as I said, even at the aggregate level, it is not particularly material. There are mitigations both through regulation, but also for looking at alternative sources as well. There are plenty of supply chain opportunities for things like pull-up transformers in the US should we need to do that. Those are sort of some of the examples. Andy. Yes. Again, thanks for the question. Yeah.
I think there are two things to factor into thinking about the guidance we have given on overall financing costs. One is, of course, as we continue to invest heavily in our capital program, that means that although there will be increased funding costs, there will be a degree of increase in capitalized interest as well, which offsets the sort of gross impact from a funding perspective. Secondly, you will have seen that we were very explicit that our net debt increase excludes the potential proceeds from our disposals, both the completion of the energy renewables business, but also the planned sale of Grain LNG. Therefore, effectively, our guidance on the interest line does make a net assumption for the impact of those. Thanks, Andy. There does not seem to be any more questions.
Let me just say, first of all, thank you, everybody, for your kind words and comments. I guess our key message today is there's been strong performance in the first year of our five-year plan. We're certainly seeing the benefits of the resilient business model we have here at National Grid, which delivers stable and predictable outcomes. We're very well positioned with all the work that we've done in the first year to deliver on the five-year GBP 60 billion capital investment plan. With that, I'm going to thank everybody for joining us. I hope for those who are based in London, we'll see some of you this afternoon for our discussion in more detail on the capital investments, both in the U.K. and in the U.S. Thanks very much, everybody.