Good morning, ladies and gentlemen. Welcome to the North American Construction Group conference call regarding the second quarter ended June 30, 2025. At this time, all participants are in listen-only mode. Following management's prepared remarks, there will be an opportunity for analysts, shareholders, and bondholders to ask questions. The media may monitor this call in listen-only mode. We are free to quote any member of management, but they are asked not to quote remarks from any other participant without the participant's permission. The company wishes to confirm that today's comments contain forward-looking information and that actual results could differ materially from a conclusion, forecast, or projection contained in that forward-looking information. Certain material factors or assumptions were applied in drawing conclusions or in making forecasts or projections that are reflected in the forward-looking information.

Additional information about those material factors is contained in the company's most recent management's discussion and analysis, which is available on SEDAR and EDGAR, as well as on the company's website at nacg.ca. I'll now turn the conference over to Mr. Jason Veenstra. Thank you. Please go ahead.

Speaker 1

Thanks, Dina, and good morning, everyone. A bit of a change today as I'll start off right away with the financials and pass the call to Joe for the operational and outlook commentary. Starting on slide four, the headline EBITDA number of $80 million and the correlated 21.6% margin were impacted primarily by three distinct challenges in the quarter. First, based on the strong growth in Australia, we were required to incur higher than expected maintenance costs on subcontractor labor. The ramp-up curve in Australia has resulted in a lag in recruitment of our critical heavy equipment technician personnel, and the resulting contractor costs resulted in higher expenses in the quarter. Second, an abrupt stop to work in April in the oil sands region resulted in higher operational and overhead costs due to the inefficiencies associated with unplanned outages. North American Construction Group Ltd.

has been working in the oil sands for decades, and we understand the need to be agile, but the inconsistency experienced this quarter was abnormal and resulted in us incurring costs we normally could avoid through routine mine planning and resourcing. Thirdly, although the project team and workforce at Fargo progressed the project extremely well, they had an eventful corporate quarter as a settlement with the authority, and the finalization of an updated detailed plan to completion led to a significant margin adjustment in the quarter. For those familiar with project management, adjusting margins even slightly for a project that is 70% complete can be material. Excluding these items, EBITDA would have been well above $100 million and at our typical margin profile of around 27% to 28%.

These three challenges drove the financial results for the quarter but have been mitigated and addressed as Joe will describe in his prepared remarks. We included a comment here about our steady revenue growth as we posted $371 million of combined revenue, which is a 12% increase from last Q2. Australia in particular continues to impress with its consistent growth trajectory being up 7% from the first quarter of 2025 and 14% from last Q2. When we look back on Australia, the revenue of $168 million that we generated this quarter is more than double since the second quarter of 2022, three short years ago, which was $81 million on a pro forma basis. The MacKellar Group generated almost $60 million in June alone and set another company record for monthly revenue.

June's strong top line bodes well heading into a second half of 2025, and this growth rate is indicative of the demand we see in Australia. Moving to slide five and our combined revenue and gross profits. Australia was up $21 million on a strong quarter, which benefited from growth capital being commissioned and fairly stable operating conditions. Equipment utilization in that region of 76% was strong but was slightly held back from rainy conditions in April that carried over from Q1. This top line positive variance was further bolstered by higher revenue quarter over quarter in the oil sands region, which compares favorably to last year's Q2 but was significantly impacted by inconsistent demand, primarily in April. Our share of revenue generated in the first quarter by joint ventures was down $4 million from last year, primarily due to lower scopes being completed within the Nuna Group of Companies.

Fargo was consistent quarter over quarter, but that consistency factored in an approximate $8 million reduction in recognized revenue based on the updated project plan. Excluding that one-time entry, Fargo's scopes completed in the quarter were approximately 30% higher than that of Q2 2024. Combined gross profit margin of 10.7% was impacted approximately 8% by the three factors previously mentioned: subcontractor costs in Australia, operational and overhead costs in Canada from unplanned stoppages, and the Fargo settlement and updated project plan. Less prominent impacts included the continuation from Q1 into April of the rainy weather in Australia and early failures of certain components in our heavy equipment fleet in Canada. Moving to slide six, Q2 EBITDA and EBIT were down from their 2024 comparables as discussed.

The 21.6% margin we achieved is not indicative of where we see our business operating at and well below the 28% run rate we've been on since the acquisition of the MacKellar Group. Included in EBITDA is direct general and administrative expenses of $12 million, an equivalent of 3.6% of reported revenue, which is below the 4% target we've set for ourselves. Going from EBITDA to EBIT, we again expense depreciation equivalent to approximately 16% of combined revenue, which is higher than the 13% posted in 2024 Q2 and reflects the component issues we are experiencing in Canada. Again, this 16% is higher than our expected run rate moving forward, given historically we've been between 13 and 14%.

Adjusted earnings per share for the quarter of $0.02 reflects the significant bottom line impact of the challenges we've faced, with interest expense identical to last year and tax rates consistent as well. The average cash interest rate for Q2 was 6.4%. Moving to slide seven, I'll briefly summarize our cash flow. Net cash provided by operations prior to working capital of $64 million was generated by the business, reflecting EBITDA performance, net of cash interest paid. Free cash flow was neutral for the quarter based on the sustained capital spending. Moving to slide eight, net debt levels ended the quarter at $897 million, an increase of $29 million in the quarter as gross spending required debt financing. Net debt and senior secured debt leverage ended at 2.2 times and 1.5 times, respectively. With those brief comments, I'll pass the call to Joe.

Speaker 4

Thanks, Jason. Morning, everyone. I'm going to start with a brief overview of our Q2 2025 operational performance, and then I'll conclude with our second half outlook, our growth opportunities in Australia and the infrastructure markets, and our expanding bid pipeline before taking your questions. On slide 10, our Q2 trailing 12-month total recordable rate of 0.42 remains better than our industry-leading target frequency of 0.5. We continue to advance our systems and training with key focus on increased high-risk task awareness and serious accident prevention. A lot of people in our business claim safety as part of their core beliefs and culture, but when you look at their history, their promises don't match the facts. Unlike others, North American Construction Group Ltd. can demonstrate 10 years of industry-leading results from 2016 to now while showing simultaneously increasing exposure hours by more than four times.

Importantly for investors, these facts readily show our customers what a strong safety culture looks like and differentiate us from our competitors. This translates to contract wins, lower downtime, higher revenue, and lower costs. Moving to slide 11, I want to highlight some of the major achievements of Q2. The trailing 12-month revenue set another company record, with Australia leading the way and containing an impressive three-year growth rate of 28%. Just as impressive, if not more so, our business in Australia is growing at that rate and continues to improve on fleet utilization. Our Fargo flood diversion project, a highlight for our diversification efforts, enters the last year of major construction and remains on track for scheduled completion and handover to operations and maintenance teams. Soon, Fargo and the surrounding communities will have flood protection in place to quell those annual spring fears.

Our discipline management approach kept administrative costs at 3.6%, showcasing our ability to grow and support top line revenue without adding to our overheads. Our ability to handle large civil infrastructure projects with the same operational and financial success is the key to our expansion in this segment. On the corporate front, we won the biggest contract in company history last week, shortly after our Q2 close, which drove record backlog and continued our trend of 100% renewal rate in Australia. Continuing another Australian trend, this contract renewal was achieved more than two years before the previous contract expiration. On the topic of renewals in the U.S., we also renewed our Texas Thermal Coal Mine Management contract out to 2028. Lastly, on the financial front, we completed a $225 million offering of senior unsecured notes, providing liquidity for our future growth opportunities.

We ended Q2 with what I believe are two critical additions to our senior team. We've hired a VP of Asset Management and a VP of Infrastructure and Growth. Stuart and Melanie are industry tops in their respective fields and will play major roles in leading our growth and diversification strategies. I expect to be sharing their accomplishments with you frequently in the coming quarters. On slide 12, we've combined the Australian and Canadian fleets to form a global utilization rate as measuring our global utilization becomes more and more important to our decision-making. A 75/25 Australian to Canada weighting was chosen as it is roughly proportionate to our respective earnings expectations. Despite our Q2 setbacks, our global utilization rate is trending up, and our continued prudent fleet management is expected to deliver utilization in the second half of the year in our target range of 75% to 80%.

Moving on to our outlook for the remainder of the year, slide 14 highlights the three steps which are mainly cost-related that bridge our Q2 EBITDA margin results to our H2 expectations. To start, the Fargo settlement that is now behind us is one-time in nature, and we have high confidence in the forecast that's made to complete as we have thoroughly reviewed the forecast as have our other partners. In Australia, we expect lower costs as we reduce our reliance on subcontracted skilled trades, and importantly, we're ahead of schedule in those reductions through July. Lastly, in our oil sand business, we expect more consistent operations as our customers have no planned plant outages in the second half of the year as historically lower weather exposure. On slide 15, we've provided an outlook for the second half of 2025 and highlighted any variance to previous H2 expectations.

As I said in my letter to shareholders, we remain confident in delivering second half year results consistent with our original expectations, aside from our oil sands business. Although these oil sands changes negatively impact our second half EBITDA and EPS, the unchanged combined revenue and free cash flow expectation reaffirms a strong finish to the year and sets us up to be back on historical growth trends for 2026. On slide 16, we highlight why our long-term growth targets remain intact, with anticipated organic revenue growth of 5 to 10% annually, underpinned by ongoing Australian growth, new infrastructure projects, which I'll detail further on the next slide, and new mining projects and opportunities to displace higher cost contractors in Australia and Canada that will further enhance fleet utilization and operational diversification. On slide 17, we detail the growing civil infrastructure opportunities in North America.

Aging infrastructure, energy transition, climate resiliency, and tariff threats pushing nations to seek more resource independence, all fueled by federal stimulus, are driving what we believe is a vastly growing opportunity in the civil infrastructure markets, with spending uptick kicking off in 2026. This infrastructure growth is coming off a major previous uptick in 2023 and positions us well to support major general contractors who are at capacity as either a partner or a subcontractor. We expect to have secured two strong project teams to pursue our top 10 projects before year end and maintain our plans to increase infrastructure to around 25% of our overall business by 2028.

As I mentioned earlier, our VP of Infrastructure and Growth is now in place, and although she has only been with us a bit over a month, she has hit the ground running and has already shown the skills and tenacity to fit right in at NACG. This gives me confidence in our ability to achieve our infrastructure goals. Slide 18 highlights a strong bid pipeline, including our top 20 infrastructure projects totaling around $2 billion. The big blue spot in the middle is now gone, as that is the $2 billion contracted win at the Cleveland Coal Mine we announced last week. The remainder of the bid pipeline remains essentially unchanged as no other significant bids in that procurement have been awarded.

Although not a sizable enough project to warrant a press release, it should also be noted that our mine management contract extension at the Texas Thermal Coal Mine never entered the bid pipeline, and we were able to negotiate that extension directly with our customer. Lastly, regarding capital allocation going forward, we have been active in our NCIB, having purchased and canceled around 680,000 shares since inception to quarter end, demonstrating our commitment to shareholder-focused allocation. We have increased liquidity with our high-yield rate and an expected midpoint of $100 million in free cash flow for the second half of the year, which gives us confidence to continue investing in shareholder-friendly ways.

It provides us funds should we need to settle our remaining convertible debt of cash, which is now a current liability due to the end of Q1 2026, and provides additional funding should we need letters of credit for future infrastructure bids or find other high-return investment opportunities. In summary, while Q2 was not an easy time for us, we're looking forward to a strong back half of the year and are excited to share more operational updates with you as we move towards the end of the year. With that, I'll open up for any questions you may have.

Speaker 6

Thank you. We will now begin the question and answer session. To ask a question, please press star one on your touch-tone phone, and if you wish to withdraw your question, you can press star, then the number two. Once you have completed your question and would like to return to the queue, please press star one again. If you're using a speakerphone, please lift your handset before pressing any keys. One moment, please, for your first question. Thank you, and your first question comes from the line of Aaron McNeill from TD Cowen. Please go ahead.

Speaker 3

Hey, morning all. Thanks for taking my question.

Speaker 5

Morning, Aaron.

Speaker 3

Jason, you sort of alluded to it in the prepared remarks. I'm hoping you can help us a bit with sort of future free cash flow generation. I know there's no guidance out for 2026 yet, but I'm hoping you can just quantify the challenges this year, including the Fargo settlement, the margins in Australia and Canada, at least to the extent that you don't expect them to recur next year. Just give us a sense of what you expect will be the big moving pieces on free cash flow generation. I'm thinking about, you know, again, Australian margins, sustaining growth capital, or anything else you think is relevant. Again, like not to put too fine a point on it, I just want to think about sort of the moving pieces there and if you can give any visibility to an improvement in free cash flow in 2026.

Speaker 1

As far as it relates to the second half, we see about a $20 million working capital good guy in the second half from collections that slipped from June into July. That sort of reconciles the reduction in EBITDA, but the consistency in free cash flow. As far as the first half goes, the EBITDA difference from expectation to actual fell to free cash flow, essentially. CAPEX came in slightly higher than expectation, about $10 million higher, but the primary driver of the free cash flow difference is the difference in EBITDA. JV, the Fargo settlement and the $8 million impact, we do collect from Fargo on a % of completion basis, so that does have an impact on free cash flow as well. Essentially, the EBITDA impact does fall to free cash flow for the first half.

Speaker 3

Right. I'm just thinking more about 2026. I guess not to put too fine a point on it, but, you know, the sustaining capital is higher, growth capital is higher. Are those sort of the right, you know, is the run rate this year something that we should think about into next year?

Speaker 1

No, we would expect the 2026 sustaining CAPEX range to be the $180 million to $200 million that we had for this year. Some of the component issues we experienced in Canada were driving that overage, and we don't expect those to happen again in 2026. We would expect a similar free cash flow target, call it $130 million to $150 million for 2026, when we guide in October.

Speaker 3

Got it. Joe, one for you. I'm just looking at not the Q2 presentation, but the August investor presentation that just hit your website. You speak to 15% Australia growth in 2024, 25% in 2025, and then a consolidated long-term growth rate of 5 to 10%. I realize that's a top line target, but how's the Australian labor strategy evolving, and what do you think is a practical sort of ceiling on your potential revenue growth in Australia before you get into the negative margin outcomes that we saw with Q2?

Speaker 4

I think managing a 5% to 10% growth rate is very reasonable. Obviously, we've had a bit higher than that. You know, we also started the copper mine up in New South Wales. That wasn't an area we had been operating in previously. Skilled trades is an issue that always rises its head in our business at certain times. We react to it fairly quickly. I think we've been through this before. They're reoccurring items, and we've addressed it. I feel very comfortable that we'll have worked our way out of this in the second half of the year down there. Like I said, I think we already had a good head start on it in July. At a lower growth rate, it's much easier to manage. The higher the growth rate in any particular area, the more pressure it puts on any kind of hard-to-get trades like that.

Speaker 3

Gotcha. Okay, thanks. I'll turn it back.

Speaker 5

Thanks.

Speaker 6

Thank you. Your next question comes from the line of Kevin Geaney from Thomson Reuters. Please go ahead.

Speaker 5

Good morning, Joe, Jason. It's Kevin on for Adam. Despite the shutdown, revenue growth in Canada was still strong. I think about 20% year over year. Would revenue have been even stronger without the shutdown, or did the shutdown impact costs more than sales?

Speaker 4

Revenue, it was a direct relationship to revenue. The cost and the inefficiency is when you have those kind of abrupt shutdowns, laying people off and hiring them back on takes time and money and carryover of overheads. You don't want to lay off your entire staff and then try and bring them back three weeks later or a month later. Those were direct impacts. We don't see that happening again because it was predominantly related to their timing of a major turnaround in their plant.

Speaker 5

Do you think that turnaround was just a one-time off turnaround, or that oil sands will be smoother in H2?

Speaker 4

I think generally we do those about every three or four years, but we actually met with them in early May and had discussions on what those impacts were to us and how it negatively impacted them. I think we've got a good understanding and relationship that hopefully the next one that happens to be three years down the road or whatever, we've got plans in place to schedule around it to where you don't have an abrupt shutdown of work and then bring it back online. That's very expensive and it creates issues across the board, operationally, safety costs. We've had those discussions and I think our clients understand it. It was an unfortunate situation in Q2 and hopefully we can plan our way around it in the future.

Speaker 5

I appreciate the color on that. Maybe for you, Jason, on the guidance, how are you guys looking at Q3 versus Q4? Are you expecting strong results in Q4 or Q3? Should they look relatively similar from an EBITDA standpoint?

Speaker 1

Yeah, there's some puts and takes, but it's basically flat quarter over quarter. You know, with Fargo will be a little stronger in Q3, but Australia is going to be stronger in Q4. It works out to pretty much equal quarters from an EBITDA and EPS perspective.

Speaker 5

Perfect. I'll turn it over. Thanks, guys.

Speaker 6

Thank you. Your next question comes from the line of Prem Kumar. Please go ahead.

Speaker 0

Hey, good morning, team. I had a couple of questions, so please bear with me. My first question is on if you could expand on any changes to your OEM partnerships. You mentioned in the letter that you've expanded your partnership with OEM and dealer networks. Can you please kind of help us explain what those changes are? Also, are there any changes to your physical network in Fort Mac over the last quarter or so with regard to these partnerships? Thank you.

Speaker 4

Yeah, you know, I think this was actually something we transitioned to last year was a partnership with our Caterpillar dealer in a component remanufacturing side for a certain portion of our components. That's gone very well, actually. That was the driver for switching to that was based on the component issues we were having last year. We've had some lesser component issues that Jason mentioned. Those were actually in some of the OEM products. They weren't the same components as we were talking about last year. We do have, we've had a very positive response from our dealer. Right now, it's basically making sure parts are available and on the shelf for any issues and then troubleshooting that to prevent reoccurrence. You know, those partnerships are very strong for us with our major Caterpillar dealer.

Speaker 0

Okay. No changes to your existing footprint in Fort Mac other than this partnership with OEMs?

Speaker 4

Yeah, we have the same relationships with clients and our equipment dealers that we've had in the past.

Speaker 0

Okay. Can you please expand on the contract labor issues in Australia? I was a little surprised, I guess, based on your commentary from the past where you mentioned you've seen growth in Australia. I was kind of hoping you would be prepared for the exceptional growth in Australia. The labor issue took me by surprise. Could you please expand on that, please?

Speaker 4

Yeah, you know, for the 40 years I've been in the industry, the service skilled trades are always difficult. With us, it's heavy equipment technicians. We've built systems around how we increase and develop our own mechanics. When you have a very high growth rate, you go into new areas like we did in Australia, it's often difficult to find those guys. We react very quickly. In the near term, you subcontract out those services. It's not an unusual event in the industry, but it's one we learn to react to. It's much easier when you're on a 5% or 10% growth rate than when you're on a 20% to 30% growth rate. It's not something we're ill-prepared for. It's just harder to do with that kind of growth than with a lower rate of growth.

It's an area where we have our HR team focused on how we develop and access those people faster when we need them for fast growth. It's always an issue in industry, has been for forever. It's the guys that react quickly and then develop long-term solutions, which I think we've demonstrated we can do.

Speaker 0

Okay. On your contract backlog, any concerns about having around 50% of the backlog coming from one site, I think in Australia?

Speaker 4

I think that's our biggest client right now, and we've signed a five-year term, so it's fresh in the books. It's just the timing of things. When we get two years in on that contract, something else will be on the top. Hopefully, a big infrastructure project is my expectation. At this point in time, just because we were only awarded that contract a week ago, it sits that high in the backlog %. As we advance and renew and win others, you'll see that % drop. No, it doesn't worry me.

Speaker 0

Okay. I'll just do more. I apologize for asking quite a few questions today.

Speaker 4

You're ready to get to the bonus round, Fred?

Speaker 0

I just wanted to ask, how are the prospects in infrastructure work shaping up? I think you talked about hiring the new Head of Infrastructure and then the Vice President as well. Could you expand on how you're the progress on building up the team and then, you know, where in the process are you guys right now?

Speaker 4

Yeah, if you look at that slide on the infrastructure, it actually lists our top 10 projects. What we're seeing is a significant increase in infrastructure projects that really fit in our wheelhouse, which are ones that have major earthworks. We're seeing it across Canada and the U.S., seeing just getting into the Australian side as well. There's a lot of pumped hydro kind of earthwork stuff around the energy transition. There's a lot of stuff like Fargo, you know, climate resiliency projects where areas that used to flood once every 20 years are flooding every four years. Now they want to build flood diversions or beef up their levees. We see a lot of infrastructure building access into, like in Canada, you know, access up to the Ring of Fire or the Grays Bay Arctic port.

There's opportunities, and those fit into our wheelhouse as far as building that infrastructure, those roadways, those access ways through remote Arctic areas. You can see the project list on that slide, but if you go look at them, what you'll find is they're very much earthworks-oriented. Historically, we never saw this level of earthwork side in the infrastructure. Where we sit right now is putting together project teams. We're going to look at partners similar to the guys we have at Fargo. They actually own a schooner balloon. We'll look at partners that fit those particular projects well that we think have the highest rating, if you would, in teams. We're going to look at a team with them by the end of the year. I have two of them.

Then take those teams, and we expect to win a couple of projects and have 25% of our work in the next couple of years.

Speaker 0

Okay. Thank you. I'll ask my last question. With regard to free cash flow, I think Jason mentioned normalized for maybe like next year, free cash flow would be about $120 to $150 million. Looking at some of your older presentations, like some 2023, what you were guiding just for the Canadian division was around $100 to $115 million free cash flow. Then came the MacKellar acquisition. I'm a little surprised that your combined normalized free cash flow for next year or for a normalized year is almost as close to your upper guidance for just the Canadian division just about a year and a half, two years ago. Also considering the fact that over the last 12 months, you've had free cash flow of $20 million for a company with a replaceable asset value of over $4 billion.

That's, in my opinion, pretty poor returns for a high $4 billion asset. I think the market agrees too, especially with regard to where the share price is now. Can you expand, can you help me with regard to the free cash flow? What's the team doing to improve that? I guess, does the team also have the same notion on the free cash flow being low right now?

Speaker 4

Absolutely. We think it's low. That's, but you know, we see it coming back to that midpoint of $100 million over the next six months. You know, there's a lot more questions in that than I can answer, Bram, but yeah, we're very confident in our free cash flow projections and it growing, going into and going back to normal in 2026.

Speaker 0

Okay, thank you so much. I'll end it with that.

Speaker 5

No worries. Thank you.

Speaker 6

Thank you. Your next question comes from the line of Sean Jack from Raymond James. Please go ahead.

Speaker 3

Morning, guys. I just wanted to ask one question on Australia. I was just wondering how we should be thinking about gross margin moving into the back half here. It seems like efforts have definitely been taken to mitigate the skilled trade stuff. Are we going to be looking at a more gradual improvement, kind of a step change in the third quarter? Any color would be great.

Speaker 4

Yeah, I don't know what the number was. It'll be half, Jason, you'll have to answer that. We expect to be back to what we'd originally projected in our original guidance.

Speaker 1

Yeah, we're in the low 20% for gross profit margin, Sean. As Joe mentioned in his prepared remarks, the subcontractor issue is rectifying quickly. We got through most of it in July. We expect to be a percentage up in Q4 over Q3. Low 20% is the expectation for Australia.

Speaker 3

Okay, perfect. One more for me. You guys also just talked about kind of putting the project teams together on the infrastructure side and kind of getting the right people in place. Wondering if you guys have any visibility on what that sort of bid pipeline looks like right now from a timing perspective. How early could investors see, you know, realistically new projects from the infrastructure side coming into the fold?

Speaker 4

There are actually some that are on very fast tracks. Additionally, in looking at ones that we may not be part of the bid team, but we can look at from a subcontractor standpoint, those opportunities could be as early as summer of 2026. Most of the other ones where you're actually bidding as a team, a design-build kind of thing, I'd say probably more out into the 2027 standpoint. If you look at the bid pipeline, those light blue dots in the very bottom line, those are where those projects are expected to start. Some of them are starting with just engineering and design, and that construction could be out. You could win a project in 2026, but it might just be engineering and design. You don't start the construction until 2027. There is some opportunity for 2026, but I think the biggest ones are in 2027.

Speaker 3

Perfect. That's all from me, guys. Thanks.

Speaker 5

Thanks, Sean.

Speaker 6

Thank you. Your next question comes from the line of Kazim Nakvi from National Bank Financial. Please go ahead.

Speaker 5

Good morning, guys. Kazim here on for Kazim Nakvi.

Speaker 0

Morning, Kazim.

Speaker 5

Most of the questions have been asked. I just was wondering what the JV forecast adjustment for Fargo means for the future profitability of that JV. Do you guys expect it to be profitable for the year? What should we expect going forward for 2026?

Speaker 4

Yeah, that change is made for the end result of the project. We expect to maintain that margin, hopefully improve upon it. We're very confident in where that margin sits. We reviewed that forecast. This was also part of the overall agreement we made with the authority that settled all the old claims. We don't have anything hanging over us from the past now, and we're just looking forward to complete it. We're in the last kind of quartile of that work and expect to hand it over to operations and maintenance at the end of next construction season next year.

Speaker 5

Great, thank you. I think.

Speaker 4

That was our project too, Kazim. It wasn't a major loss of margin. It's just the fact that you're 70% complete that it made a big impact in Q2.

Speaker 5

Great, it's just more like a one-time thing.

Speaker 4

Absolutely correct.

Speaker 5

Okay. Great. I think you already touched upon this about the Australian labor issues. Should we assume that this will not continue on in 2026, or is this the new steady-state margin given that, you know, labor costs have gone up?

Speaker 4

No, we wouldn't expect this in 2026. It's always cyclical, and skilled trades are always an issue in our industry. They just come up. It just puts more pressure on you when you have a high growth rate, but you know, adapting and growing and building our own development processes in our HR, we've demonstrated this in the past. We've felt these pressures before, and we know how to deal with it. I don't expect this to reoccur in 2026, no.

Speaker 5

Thank you. That's it for me.

Speaker 6

Thank you. Your next question comes from the line of Krantz Thompson from CIBC. Please go ahead.

Speaker 3

Good morning, guys. I'll start on the guidance for the oil sands. It looks like you lowered your margin expectation there for H2, but I'm just a bit confused because I was under the impression that the Q2 turnaround activity was really the cause of that impact this quarter and that was behind us. It feels like that may not be the case. How should we think about that for 2026 margins in the oil sands?

Speaker 4

That is behind us. I do think we had some issues with some components, some different components. We have lower revenue projections in the second half, we always did. There is not the same efficiency, and these component issues, which we've rectified as far as the impacts to us operationally, our dealers have responded by putting parts on the shelf. It is probably another six months before we get the solutions in place to prevent reoccurrence. I wouldn't expect that to continue on into 2026. I would expect we're back at normal margins, very similar, my guess, to what we started the year with as far as our expectations.

Speaker 3

Okay. The impact for H2 margin, Joe, is purely parts related?

Speaker 4

We have a lower revenue per month, if you would, than we did in H1, and so there's a little bit of loss of efficiency and overheads in that. There is still some component-related issues, and they're different than what we had last year. We have the OEMs involved in this, where previous ones I spoke about last year were actually partnerships we had that weren't with OEMs or OEM dealers. They've already reacted. We have what we would call stage one, which is containment of an issue, and then we're going to resolve to prevent it and put a solution in place. They're actively working on that with our team.

Speaker 3

Okay. Thinking back to the oil sands contract that you had won in late 2024, the committed spend was $500 million. You'd expected that represents a third of the total work to be performed across the mine site. How much of that $500 million committed spend have you already worked through? How confident are you in that one-third assumption that you originally went in with?

Speaker 4

I'm confident in the one-third as far as the amount of work that gets done every year, the amount that comes off backlog at any one time. It's the same for us that their commitment to us is the same as our commitment to them. I actually don't think the backlog burn changes the total amount of revenue we do with those clients. I don't know, Jason, what's the number we've gone through, $150 million or so?

Speaker 5

Yeah.

Speaker 4

Yeah, it's somewhere in that $150 to $200 million range. I talked about it. The backlog will probably consume faster, and we look at that as a good opportunity going forward to talk to our clients about increasing those commitments over these four years.

Speaker 3

Okay. In terms of maybe just addressing the volatility that you've experienced with your oil sands work, I think going forward, is there a way to shift the way these contracts are structured to help guard against this volatility? I guess, like what's the long-term solution to try and manage the amount of volatility we've seen in that contract?

Speaker 4

For us, it's really maintaining a good, open relationship with our clients so that we can communicate and plan together. That didn't occur in this instance very well. We had discussions afterwards, and I think we've reset that. From a contracting standpoint, it's for contractors to get more leverage when we have higher demand than supply, and then you can get stronger in your terms and conditions. It's just a matter of where that sits in the market at the time, like any other contracting business.

Speaker 3

Okay. Just last one on the oil sands. Slide 23, you highlighted the replacement value of the fleet overall. Can you break out for us what the replacement value is for your oil sands fleet?

Speaker 4

Yeah, I'm sure Jason can get that to you, Chris. I don't know if he knows it off the top of his head.

Speaker 3

Sure. No problem. Okay. Last question just on Australia. When I look back at 2023, it looks like gross profit margins were pretty strong, like mid-20% to low 30%. Now for H2 2025, we're talking about low 20%. I'm just wondering, what's changed in the business that has seen that margin shrink over time?

Speaker 4

I don't have the exact bridge for you. I know what the difference is. We've expanded some of those marketplaces and added maintenance labor. It's just a mix of work. Your highest margin, if you do a straight dry rental, I don't know if you're familiar with that term, Chris, but if you just rent a truck, it does have the highest margins because that, if you rent that truck and you provide maintenance for it and the labor, the margins on labor aren't as high. It's really just a mix of work. It's not the same work having reduced margins.

Speaker 3

Okay, that's good. Thanks for clarifying that. I'll turn it back. Thank you.

Speaker 6

Thank you once again. That is star and one to ask a question. Your next question comes from the line of Kevin Geaney from Thomson Reuters. Please go ahead.

Speaker 5

Hey, guys. Appreciate you letting me jump back in. I just wanted to ask, has there been any thought or continuation of thought on moving more heavy equipment from Canada to Australia?

Speaker 4

Absolutely. We've moved some small pieces. Actually, we've got four more trucks we're shipping over there right now. It's not a huge amount of gear. If you look at the bid pipeline, Kevin, you'll see a big blue dot on the top row. It's in 2027, and that's probably our biggest opportunity to move a good chunk of fleet that isn't committed in Canada right now. That would be our biggest opportunities. We're still moving a few pieces here and there, and we're bidding other work outside of oil sands that we look to use and increase our utilization of our smaller end fleet. Oil sands demand is still very strong, and it's a business that we still see staying at that level of revenue for years to come. We will look to take our fleet and right-size it to maximize our utilization and return.

Those kind of opportunities like that big blue dot in 2027 you'll see are the biggest ones we see, and we see more of them coming up after that.

Speaker 5

You guys wouldn't preemptively move it. You would wait until you win the contract?

Speaker 4

Yeah, they're very high cost to move stuff. It's not the, and it takes a significant amount of time to get it overseas. No, we would have won a contract, you know, six months, eight months in advance of when we would shift the fleet. It takes about roughly six months between tear down, get it over there, and get it set up. You know, we've moved 30-odd pieces over there now, so we're pretty familiar with that process.

Speaker 5

Okay.

Speaker 4

We would expect that big blue dot that starts in 2027, we would expect to win that in mid-2026, such that we would have time to move equipment over.

Speaker 5

Thanks, Joe. I appreciate the color. Maybe just quickly on Nuna, what's the outlook for revenue at Nuna going forward?

Speaker 4

I think, you know, it's pretty modest this year, and I think it's, but it's pretty much on plan. There's real big opportunities coming up, even on the infrastructure side, which we would probably partner with them on in some of these northern opportunities. For example, if you're familiar with the Grays Bay Arctic port and some of the Arctic jobs that are up there, Baffinland Iron Mines, those are all Nunavut and Kitikmeot territory, in particular for Grays Bay. We see great opportunities for us and for Nuna in those. Just on the northern mining side, we're seeing more mines start to get permitted and expand. That's generally a slow process. This was always anticipated to be kind of the trough year for Nuna just because of the way the industry dollars were looking to be spent.

We see from 2026 out, there's some great opportunities for them to continue to grow.

Speaker 5

Thanks, guys. I appreciate the color.

Speaker 1

Thank you, Kim. Thanks, Kevin.

Speaker 6

Thank you. This concludes the Q&A section of the call, and I will pass the call over to Joe Lambert, President and CEO, for closing remarks.

Speaker 4

Thanks again, everyone, for joining us today. We look forward to providing next updates on our closing of our third quarter results.

Speaker 6

Thank you. This concludes the North American Construction Group Ltd. conference call regarding the second quarter ended June 30, 2025. You may now all disconnect.