Sign in

You're signed outSign in or to get full access.

RE

RARE ELEMENT RESOURCES LTD (REEMF)·Q4 2014 Earnings Summary

Executive Summary

  • Q4 2014 net loss was $2.9M ($0.06 per share), improving from $5.7M ($0.12) in Q4 2013 and better than Q3 2014’s $3.6M loss ($0.08), reflecting reduced exploration and admin costs .
  • Year-end cash and equivalents were $10.1M, down from $12.9M at Q3 and $23.9M at year-end 2013, highlighting ongoing burn and funding needs .
  • Permitting timeline slipped: Draft EIS now expected in H2 2015 (from spring), final ROD in H1 2016; earliest commissioning remains mid-2017, pushing project de-risking milestones into 2015–2016 .
  • Strategic progress continued in test work (elemental separation) and feasibility activities; alternatives selection by USFS enables near-term permit applications .
  • Consensus estimates were unavailable from S&P Global for Q4 2014; comparisons to Street are N/A at this time (consensus unavailable via S&P Global).

What Went Well and What Went Wrong

What Went Well

  • Lower quarterly and annual losses driven by reduced exploration/evaluation spend and corporate admin costs; Q4 net loss fell to $2.9M from $5.7M YoY, with exploration down $2.4M and admin down $0.3M in the quarter .
  • Continued technical progress: “We will look to expand on the positive results we have had to date on elemental separation test work and will continue the additional technical work necessary for a feasibility study.” — Randall J. Scott, CEO .
  • USFS alternatives selection completed; company expects to apply for other state and federal permits over the next few months, advancing the permitting pipeline .

What Went Wrong

  • EIS timeline delays: Draft EIS now H2 2015 vs original schedule; final ROD H1 2016. Permitting application timing slid to Q1 2015; commissioning pushed to mid-2017 (from late 2016) .
  • Material funding need: Company expects to raise $45–$60M over the next two years to complete EIS, FS, detailed engineering, and a 1–3 tpd demonstration plant .
  • Cash drawdown: Year-end cash fell to $10.1M from $23.9M prior year; net cash used in 2014 was $13.8M (though improved vs $23.6M in 2013) .

Financial Results

Quarterly trend (Q2–Q4 2014)

MetricQ2 2014Q3 2014Q4 2014
Revenue ($USD Millions)$0.0 $0.0 $0.0
Net Loss ($USD Millions)$3.1 $3.6 $2.9
Diluted EPS ($USD)-$0.06 -$0.08 -$0.06
Cash and Equivalents ($USD Millions)$16.1 $12.9 $10.1

Year-over-year comparison (Q4 2014 vs Q4 2013)

MetricQ4 2013Q4 2014
Net Loss ($USD Millions)$5.7 $2.9
Diluted EPS ($USD)-$0.12 -$0.06
Cash and Equivalents ($USD Millions)$23.9 $10.1

Notes:

  • Company states no production-related revenue at this time; revenue is effectively nil across periods .
  • Q2 and Q3 net cash used were $3.7M and $3.2M, respectively (as disclosed), underscoring burn rate ahead of 2015 milestones .

Guidance Changes

MetricPeriodPrevious GuidanceCurrent GuidanceChange
Draft EIS availability2015Spring 2015 (USFS intended to make up time) Second half of 2015 Lowered/Delayed
Final Record of Decision (ROD)2016N/A (not previously specified)First half of 2016 New
State/federal permit applicationsQ4 2014 → Q1 2015Expected in Q4 2014 Now expected Q1 2015 Delayed
Commissioning date2016–2017Late 2016 Mid-2017 (earliest) Lowered/Delayed
Financing plan2014–2016N/ARaise $45–$60M for EIS, FS, engineering, demo plant New specificity

Earnings Call Themes & Trends

(Company did not furnish an earnings call transcript; themes reflect press releases.)

TopicPrevious Mentions (Q2 2014, Q3 2014)Current Period (Q4 2014)Trend
Permitting/EIS timelineDraft EIS anticipated early 2015; scoping completed in April; public scoping summary in July . Alternatives analysis delays; permit applications slipped; USFS intent to make up time Draft EIS anticipated H2 2015; ROD H1 2016 Slower; calendar pushed right
Commissioning timingN/A in Q2 Shift from late 2016 to mid-2017 Later start
Elemental separation test workOngoing analysis and identification of potential technology partners Expand on positive results; additional technical work for feasibility study Continued progress
Demonstration plantPlan for 1–3 tpd demonstration plant to minimize start-up risk Reiterated as part of 2015 programs Ongoing preparation
FinancingN/A in Q2 ; noted cost containmentNeeds $45–$60M over the next two years Higher funding requirement clarity
Offtake engagementDiscussions with potential partners based on +97% pure TREO concentrate Distribution of separated products to potential offtake partners Commercial outreach ongoing

Management Commentary

  • “We made great progress in advancing our Bear Lodge Project in 2014… we intend to apply for other necessary permits over the next few months. With its ideal location, large long-lived resource, heavy concentration of the more valuable, critical rare earth elements and solid project economics, we believe the Bear Lodge Project is in an excellent position to help rebuild America’s rare earth supply chain…” — Randall J. Scott, President & CEO .
  • “During the quarter, we released a very positive Preliminary Feasibility Study… success in our test work on an innovative approach to separation and further optimizing of our proprietary recovery process — both of which will contribute to lower costs.” — Randall J. Scott .
  • “We have seen some delays by the U.S. Forest Service… This has impacted the Company’s ability to complete the application process for permits… we are shifting our anticipated timing for Project commissioning from late 2016 to mid-2017.” — Jaye T. Pickarts, COO .

Q&A Highlights

  • No Q4 2014 earnings call transcript was found; the company appears to have furnished results via press releases without hosting a public call during the period.
    (No transcript available in the document set; results sourced from 8-K press releases .)

Estimates Context

  • Wall Street consensus estimates for Q4 2014 were unavailable from S&P Global at the time of this analysis; therefore, explicit comparisons to Street EPS and revenue are N/A.
  • We recommend assuming no formal analyst coverage for quarterly estimates given the company’s exploration-stage status and lack of production-related revenue .

Key Takeaways for Investors

  • Regulatory path is the principal near-term driver: watch for Draft EIS in H2 2015 and final ROD in H1 2016; slippage directly affects commissioning and cash runway .
  • Commissioning target moved to mid-2017; de-risking hinges on demonstration plant execution and feasibility work milestones .
  • Cash burn persists: year-end cash $10.1M vs $23.9M prior year; funding plan of $45–$60M over two years will be a key overhang until capital is secured .
  • Technical progress continues (elemental separation and process optimization), which, if validated at demo scale, may improve project economics and partner interest .
  • No revenue yet; focus remains on permitting and development — traders should expect news-driven volatility around permitting milestones and funding announcements .
  • Cost discipline helped narrow losses; continued containment may extend runway ahead of permitting and demo plant milestones .
  • Offtake engagement remains ongoing; distribution of separated product samples could act as validation signals to the market and potential financiers .