Question · Q4 2025
Aditya Gandhi asked for an initial estimate of OGE's portion of the Seminole to Shreveport 765 kV transmission line project, given SPP's $2.4 billion estimate. He also inquired if the 1 gigawatt data center contract's capacity needs would be met through the current RFP process and existing plans, and asked about the customer protections being built into the large load tariff framework.
Answer
CFO Charles Walworth provided a preliminary estimate of OGE's portion of the transmission line being on the order of 20% of the current capital plan, noting it's early stages. CEO Sean Trauschke added that routing is still to be determined. Charles Walworth confirmed that the data center contract is integrated into the IRP numbers and will be approached holistically through the RFP process, with customer protections including minimum terms and collateral requirements to ensure fair share payment.
Ask follow-up questions
Fintool can predict
OGE's earnings beat/miss a week before the call
