    GRYP Q4 2024: Captus to deliver 6MW by early 2025, 100MW by 2026

    Reported on May 12, 2025 (After Market Close)
    Pre-Earnings Price$0.17Last close (Mar 31, 2025)
    Post-Earnings Price$0.17Open (Apr 1, 2025)
    Price Change
    $-0.00(-0.35%)
    • Robust connectivity and low latency: The asset benefits from existing fiber connections from Rogers and TELUS, ensuring excellent latency and connectivity crucial for high-performance computing, which enhances its appeal to AI and HPC customers.
    • Abundant and reliable natural gas supply with green potential: Captus offers multiple natural gas pipelines, grid connectivity for redundancy, and an on-site carbon sequestration mechanism, positioning the asset for cost-efficient, sustainable power generation.
    • Geographic expansion opportunities: The management’s commitment to further exploring opportunities in regions like British Columbia suggests a strategic avenue for growth and diversification.
    • Uncertainty Surrounding Expansion Strategy: The analyst’s question about the British Columbia theme, coupled with the brief "Absolutely" response, highlights a lack of detailed strategic clarity, making it difficult for investors to assess the viability and risks of this geographic expansion.
    • Potential Distraction from Core Operations: Pursuing the British Columbia initiative may signal a diversion from Gryphon's primary focus on mining and energy asset development, potentially diluting resources and management attention.
    TopicPrevious MentionsCurrent PeriodTrend

    HPC & AI Hosting Expansion

    Discussed as a significant opportunity with early mover advantages for AI infrastructure hosting and diversification of revenue streams.

    Presented as a strategic shift from Bitcoin mining to building world-class HPC and AI hosting assets through a major Captus acquisition, highlighting multi-gigawatt development potential.

    Increased emphasis; the narrative has shifted from exploring opportunities to executing a large-scale, strategic pivot.

    Geographic Expansion Strategy

    Not mentioned in Q3 earnings call.

    Mentioned in Q4 with confirmation that the British Columbia theme remains active, hinting at future geographic initiatives.

    New topic in the current period, adding a geographical dimension that was not discussed previously.

    Robust Connectivity & Low Latency Infrastructure

    Not mentioned in Q3 earnings call.

    Introduced in Q4 with details about the Pincher Creek site’s proximity to fiber networks from Rogers and TELUS, emphasizing the importance of low latency for operational success.

    A new focus area, highlighting additional site-specific advantages for the company’s evolving infrastructure.

    Sustainable Green Power Generation

    Not mentioned in Q3 earnings call.

    Addressed in Q4 as part of the development plans at the Captus site, with the narrative tied to natural gas as an optimal energy source and on-site sustainability features, underscoring the future of sustainable computing infrastructure.

    Emergent; now seen as integral to the company’s long-term strategy for sustainable, high-margin revenue generation.

    Cost Optimization & Power Cost Volatility

    Detailed discussion in Q3 regarding current power costs, profit-sharing impacts due to Bitcoin price movements, and efforts to relocate to lower-cost power facilities.

    Revisited in Q4 with emphasis on the strategic pivot to HPC and AI hosting and the selection of natural gas for stable energy costs to mitigate volatility, linking cost optimization directly to the new expansion strategy.

    Evolving; while the operational challenges remain, the discussion now aligns more with the strategic reorientation, underscoring long-term energy optimization.

    Fleet Transition Uncertainty

    Mentioned in Q3 with discussions on the timing and conditions for moving the current fleet, underlining uncertainty and the need for minimally disruptive transitions.

    Not mentioned in Q4 earnings call.

    No longer mentioned; indicating a possible resolution or deprioritization of fleet transition uncertainties in favor of other strategic initiatives.

    1. Asset Timeline
      Q: When will the 136 MW be developed?
      A: Management expects to have 6 MW online by the end of this year or early next year, with 30 MW following soon and 100 MW by the end of 2026.

    2. Financing Details
      Q: When is financing announced?
      A: They plan to reveal detailed financing plans imminently, emphasizing a deliberate capital approach.

    3. Site Strategy
      Q: Will Captus host external machines?
      A: They remain open on whether to host external machines or operate their own fleet, pending further market developments and customer engagement, backed by their experienced management team.

    4. Acquisition Competition
      Q: How competitive was the Captus acquisition?
      A: The process was highly competitive; strong management conviction and stock participation played key roles in winning the bid.

    5. Connectivity
      Q: Is Captus well-connected?
      A: Yes, with fiber from Rogers and TELUS and its proximity (about an hour from Calgary), the site offers excellent latency.

    6. Ericsson/BC Status
      Q: What’s the status on Ericsson assets?
      A: They terminated the original agreement for 500 wells in BC but remain engaged to selectively acquire wells with better production and lower liabilities.

    7. BC Future Plans
      Q: Will BC details be provided later?
      A: Management confirmed that further updates on the British Columbia assets are forthcoming.