NRG Energy - Earnings Call - Q2 2025
August 6, 2025
Executive Summary
- Adjusted EPS of $1.73 beat S&P Global consensus of ~$1.65*, while GAAP EPS was a loss of $(0.62) driven by non‑cash mark‑to‑market hedge losses and legal reserve additions. Revenue of $6.74B beat consensus of ~$6.45B*. Adjusted EBITDA of $909M was in line with consensus of ~$909M*.
- Full‑year 2025 guidance reaffirmed and “trending at the upper end”: Adjusted EPS $6.75–$7.75, Adjusted EBITDA $3.725–$3.975B, FCFbG $1.975–$2.225B.
- Strategic catalysts: signed 295 MW long‑term retail power agreements for data centers on NRG‑owned sites (option to expand to 1 GW), raised 2025 Texas Residential VPP target from 20 MW to 150 MW, and closed a $216M, 3% TEF loan for TH Wharton ahead of planned 2026 COD.
- Capital return and balance sheet: reiterated 2025 capital plan (share repurchases $1.3B, dividends ~$345M); completed $768M buybacks through July 31 and declared a $0.44 quarterly dividend.
Values retrieved from S&P Global for estimates.
What Went Well and What Went Wrong
What Went Well
- Data center commercialization: “long term retail power agreements…295 MW…potential to expand up to 1 GW” and premium margins with protections; management emphasized this validates NRG’s strategy and pipeline of >4 GW LOIs/JDAs.
- Texas performance and segment mix: Texas Adjusted EBITDA rose to $512M (+$60M YoY), driven by improved retail margin; Vivint Smart Home EBITDA rose to $255M (+$27M YoY) on customer growth, record retention, and higher recurring margin per customer.
- Residential VPP momentum: raised 2025 Texas Residential VPP target from 20 MW to 150 MW; management noted adoption exceeding plan and strong uptake of additional smart‑home services.
Quote: “NRG once again delivered superb financial and operational performance…we have also signed our first long-term data center power agreements…confident that we are creating substantial value.” — Larry Coben, CEO.
What Went Wrong
- GAAP optics: GAAP Net Loss of $(104)M vs $738M income in Q2’24, primarily due to unrealized non‑cash MtM losses on economic hedges and a $163M increase in legal reserves; GAAP bears limited economic relevance but pressured reported EPS.
- East segment softness YoY: East Adjusted EBITDA fell to $99M (−$110M YoY) on higher supply costs to serve retail load (partially offset by retail gas margins and capacity prices).
- West/Services/Other decline YoY: EBITDA decreased to $43M (−$30M YoY) due to the Airtron sale (Sep’24) and Cottonwood lease expiration (May’25), partly offset by higher retail power margins.
Transcript
Speaker 4
Thank you for standing by. Welcome to the NRG Energy second quarter earnings conference call. At this time, all participants are in listen-only mode. After the speaker's presentation, there will be the question and answer session. To ask a question during the session, you need to press star 11 on your telephone keypad. You will then hear an automated message advising your hand is raised. To withdraw a question, please press star 11 again. Please be advised that this conference is being recorded. I would now like to hand the conference over to our first speaker today, Brendan Mulhern, Head of Investor Relations. Dear sir, please go ahead.
Speaker 5
Thank you. Good morning and welcome to NRG Energy's second quarter of 2025 earnings call. This morning's call is being broadcast live over the phone and via webcast. The webcast presentation and earnings release can be located in the investors section of our website at www.nrg.com under presentations of the webcast. Please note that today's discussion may contain forward-looking statements, which are based upon assumptions that we believe to be reasonable as of this date. Actual results may differ materially. We urge everyone to review the safe harbor during this presentation, as well as the risk factors in our SEC file. We undertake no obligation to update these statements as a result of future events, except as required by law. In addition, we'll refer to both GAAP and non-GAAP financial measures.
For information regarding our non-GAAP financial measures and reconciliations to the most directly comparable GAAP measures, please refer to today's presentation and earnings release. With that, I will now turn it over to Lawrence Coben, NRG's Chair, President, and Chief Executive Officer.
Speaker 2
Thank you, Brendan. Good morning, everyone, and thank you for your interest in NRG. I'm joined this morning by Bruce Chung, our Chief Financial Officer. Other members of the management team are also on the line and available for questions. Also with us, and I'd like to welcome Brad Bentley, who joined last week as our new Head of Consumer. Brad, he's on the call today but will not be taking questions unless you want to ask him why he's so excited to be here. In that case, he is more than ready, and I encourage you to do so. Let's begin with the key messages shown on slide four. First, we delivered strong second quarter results, completing an exceptional first half of 2025. We are reaffirming our full-year financial guidance across all key metrics and are currently trending at the high end of the ranges.
Second, we are announcing long-term retail power agreements with a data center operator for 295 megawatts, with the potential to grow up to one gigawatt over time. This validates our strategy and provides evidence of the growing interest in gas-fired power for data centers. Third, the TH Wharton Project has closed its Texas Energy Fund loan. Construction is well underway, and we remain on track for a mid-2026 completion. Finally, our Texas Residential Virtual Power Plant is off to a fast start. Early results have exceeded expectations, and we are increasing our 2025 target by more than sevenfold. Turning to slide five, adjusted earnings per share for the second quarter were $1.73, reflecting an 8% growth year over year when normalized for asset sales and retirements. For the first half of 2025, adjusted EPS was $4.42, representing an increase of 48% on the same basis.
Our performance was driven by expanded consumer margins, strong results in the gas business, record smart home retention, and favorable weather early in the year. It reflects broad-based strength across our business. On the right side of the page are some key developments from the quarter. We delivered top decile safety performance and continued executing our capital return plan. The Rockland acquisition closed during the quarter, and those Texas assets were integrated into our portfolio before the beginning of summer. We also announced the acquisition of a 13-gigawatt natural gas generation portfolio and a six-gigawatt commercial and industrial virtual power plant platform from LS Power. This transaction expands our footprint in PJM and ERCOT, strengthens our position in two of the most attractive power markets in the country, and enhances our ability to serve customers and large loads.
It also meaningfully accelerates our long-term earnings growth targets, strengthens our asset portfolio, and increases our exposure to upside from data center demand. Closing remains on track for the first quarter of next year. Our key growth initiatives also move forward. The Texas Residential Virtual Power Plant launched in the spring and greatly exceeded initial expectations, and we closed the Texas Energy Fund loan with the TH Wharton Project. Finally, we continue to scale our large load and data center strategy. We signed long-term power agreements with data center customers, advanced commercial discussions with multiple parties, and continued development at key sites. Let me now turn to slide six. Today, we are announcing, as I said, long-term retail power agreements with a data center operator. The agreement includes an initial 295-megawatt commitment served by Grid Power.
The deal also includes a 10-year initial term with options to extend for 20 years. Pricing is above the midpoint of our target range and features protected margins. Operations are expected to reach full capacity in 2030. We are actively working to expand this agreement to 500 megawatts with a long-term path to one gigawatt across additional sites. Our capital requirements are limited in this regard, and the returns are compelling. Future announcements will follow the same structure with details focused on capacity, term length, and indicative pricing. On the right side of the slide, we highlight the broader progress underway with respect to data centers. In addition to today's announcement, we have over four gigawatts of joint development agreements and letters of intent across multiple sites. Our long-term pipeline extends well beyond that.
Remember also, we have 2.4 gigawatts of natural gas turbines reserved for future development, which can be activated when supported by long-term data center contracts. This is a great moment for NRG Energy. It brings high-quality recurring cash flow and affirms our ability to serve the next generation of large power customers. We are just getting started. Moving to slide seven, our TH Wharton Project has closed its loan under the Texas Energy Fund. Construction is well underway, and the project remains on track to end commercial operations in mid-2026. NRG is proud to lead the way and will likely be the first company to bring new capacity online through this program, which supports reliability and strengthens the Texas grid. We also have two additional projects totaling 1.1 gigawatts progressing through the TEF due diligence process. With expected commercial operation in 2028, we remain confident in their advancement.
We have filed for completion bonus grants for all three projects and are on track to qualify for them. Lastly, Texas Senate Bill 6 was signed into law in June. This legislation provides new tools to support reliability and improve long-term planning in the ERCOT market. We appreciate the continued leadership of the Governor, Lieutenant Governor, Legislature, PUCT, and ERCOT in advancing policies that support system needs, enhance planning, and reinforce the long-term health of the Texas market. Slide eight provides an update on our Texas Residential Virtual Power Plant. We launched this program earlier this year through our partnership with Renew Home. It combines the reach of our retail brands, the Vivint Smart Home platform, and a compelling customer offer that delivers comfort and value while supporting our supply strategy. The long-term plan targets one gigawatt of dispatchable capacity by 2035.
The program is now active across all major brands and channels, and early engagement is exceeding expectations. Adoption of Home Essentials, the bundle which leads this program, is 15% ahead of plan. Uptake of additional smart home services is tracking near 40% in this cohort, roughly double our initial target. These are early results and may reflect lost momentum, but they point to strong underlying demand. We are increasing our VPP 2025 target from 20 megawatts to 150 megawatts of curtailable capacity. This reflects faster-than-expected progress against our long-term plan. Our focus remains on disciplined execution, long-term value creation, and delivering a best-in-class customer experience. This is a 10-year roadmap, and I look forward to keeping you updated on our progress. With that, I will turn it over to Bruce to provide the financial review. Thank you, Larry.
Turning to slide 10, NRG delivered another solid quarter of financial and operational performance with $1.73 in adjusted earnings per share and $909 million in adjusted EBITDA. Adjusted net income was $339 million, and free cash flow before growth was $914 million. Adjusted EBITDA and adjusted net income for the quarter were down year over year. However, this was primarily driven by the absence of earnings from the Airtron sale in 2024, expiration of the Cottonwood Lease in May of this year, deactivation of the Indian River Unit 4, and higher phantom stock expense as a result of NRG Energy's increased share price. When adjusting for these items, second quarter of 2025 adjusted EBITDA and adjusted net income would have been approximately $90 million and $70 million better, respectively.
NRG Energy recorded the highest adjusted earnings in the company's history through the first half of 2025, with $4.42 of adjusted earnings per share and over $2.35 billion of adjusted EBITDA, a year-over-year increase of 40% and 11%, respectively. Our exceptional finance performance over the first six months of this year reflects strong execution in each of our segments, driven by a mix of expanded margins, favorable weather in the first quarter, and excellent commercial optimization. Our Texas segment produced $512 million of adjusted EBITDA in the quarter and $811 million in the first half of 2025, an improvement of over 13% and 20%, respectively, from the same periods in 2024. These results were driven by strong performance at the plants, increased retail margins, and favorable weather in the first quarter.
These contributed to adjusted EBITDA of $99 million in the second quarter and $573 million through the first half of 2025. Performance in the first half of 2025 outpaced the same period for 2024, largely driven by higher margins from our natural gas business due to favorable weather in the first quarter. Our West Services Other segment had an adjusted EBITDA of $43 million in the second quarter and $120 million for the first half of 2025. The segment realized higher retail power margins in the West, which were offset by the absence of earnings from the sale of our Airtron business in 2024 and the lease expiration at the Cottonwood facility in May 2025 when compared to the same periods of the prior year.
Our smart home business continued its impressive momentum, achieving an adjusted EBITDA of $255 million in the second quarter and $531 million for the first half of 2025. The segment continues to see consistent customer growth, expansion to its recurring service margins, and record customer retention at over 90%. Free cash flow before growth was $1.207 billion in the first half of 2025 and $914 million in the quarter, exceeding the same periods in 2024 by $584 million and $251 million, respectively. The year-over-year increase is driven by our adjusted EBITDA growth through the first six months of the year and the timing of certain working capital items. We expect some of the favorability related to working capital to unwind in the second half of the year as receivables and payables settle in their normal course.
As we shared during our first quarter earnings update, we are reaffirming our 2025 financial guidance across all metrics and would continue to trend at the upper end of our guidance ranges. Moving to slide 11 for a look at our updated 2025 capital allocation. We began the year with just over $2.6 billion comprised of unallocated excess cash from 2024 and the midpoint of our free cash flow before growth guidance target for 2025. The only change from what I shared in the first quarter call, denoted in light blue, reflects an update to our liability management for a marginal increase in amortization payments. These incremental payments relate to a $1 billion upsize in our existing Term Loan B facility executed in July.
This increase to the facility will primarily be used for replenishment of capital employed for the acquisition of assets from Rockland Capital, redemption of principal related to our convertible senior notes, and the continued development of our Texas new builds. Our plan to execute $1.3 billion in share repurchases remains unchanged. Through July 31, we executed $768 million in share repurchases, or nearly 60% of the annual total, at a weighted average price of $112.74. Finally, we are now showing $35 million of unallocated capital, which we will allocate over the remainder of the year. NRG posted impressive first-half financial results, and we are laser-focused on delivering strong results for the balance of the year. I look forward to updating you in subsequent quarters on our strong execution and financial performance. With that, I'll turn it back to you, Larry. Thank you, Bruce.
We've just completed the strongest first half in NRG history. Our core business continues to exceed expectations, our people continue to perform at a high level, and our opportunities have never been greater than today. This is an exciting time for our company. We announced the acquisition of Premier Natural Gas Assets and the leading CNI virtual power plant platform. We launched a new residential virtual power plant offering, advanced our large load strategy, and signed long-term power agreements with a data center operator. We secured a Texas Energy Fund loan, closed on the Rockland transaction, and made meaningful progress across our organic growth initiatives. As my namesake Larry David would say, pretty good. We are well prepared for the balance of summer and confident in our ability to continue to deliver value to our shareholders. Operator, we are ready to open the line for questions.
Speaker 4
Thank you. Dear participants, as a reminder, if you wish to ask a question, please press star 11 on your telephone keypad and wait for a name to be announced. To withdraw a question, please press star 11 again. Please comply with the Q&A rows. This will take a few moments. Now we're going to take our first question. It comes to the line of Julien Dumoulin-Smith from Jefferies. Your line is open. Please ask a question.
Hey, good morning, team. Thank you guys very much. I got to say, another quarter. Nicely done, Larry and team.
Speaker 2
Thank you, Julien. Appreciate it. How are you?
Yeah, quite well. Thank you, guys. Hey, look, I'm speaking of, you know, delivering on new and novel topics. This 295 megawatts, can you talk a little bit about the structure here? I mean, this is kind of a novel subject for the industry. How do you think about the margin profile? I get it's a little bit commercially sensitive to talk about, but how do you think about this contributing to the bottom line or EBITDA? I mean, is this more like a residential contract in terms of margin contribution or some kind of, you know, provider of last resort CNI kind of contract? How would you frame the economics?
I would, in general, and we're not going to get, you know, too specific, as we said, Julien, because it is commercially sensitive. I think we view it closer to a CNI contract with premium margins. That's how I would think about these types of transactions. Obviously, longer duration than the average CNI contract, but as you know, we have numerous CNI customers of this size and greater. I would think of it as a CNI contract with a premium margin, and we have a variety of mechanisms to protect that margin, including things like indexing, hedging, and a whole slew of other things that we've developed in order to make sure that that margin over time is maintained.
Awesome. Excellent. Can you talk a little bit more about this partnership opportunity? It's been a little quieter on that front in recent quarters. You guys have had a lot going on. Can you talk about where you are? You guys have been, obviously, Larry, actively marketed that for over a year now. Is there more to come beyond this gigawatt? Can you talk even about the specific sites that are contemplated under this gigawatt arrangement and what that scaling up might look like? If you think about the timing.
When you're talking about a partnership, which one are you talking about? The data center agreement we announced today? Are you talking about the Kiewit part? We have a lot of great partnerships.
You're right. I'm thinking about it. The data center, leveraging your existing sites, right? The 295 getting larger, right? Is there more even beyond that as you think about your commercial activity?
Julien, as I said, I think this is just the beginning. As you know, these transactions are somewhat complicated and complex, and we're working our way through it. We're super excited about this one and super excited about the potential to expand it, as well as the pipeline that we put on the right side of the slide. From a point of view of what we're going to say about where and what, as you know, even with our regular CNI clients, we don't disclose those contracts or who they are. If the clients choose to do so, we're happy to support them and confirm it. We feel that part of our client services is really up to them to talk about themselves and their plans for the data center.
It would not surprise me if at some point these folks put out a release, but I don't know if they're going to do so.
Absolutely. The four gigawatts of letters of intent and all that as well, if any thoughts there? I'll leave it.
I think it's great to have them. Obviously, letters of intent, they're not all going to, you know, come to successful conclusions. I wouldn't model like you like to do, Julien, 150% of that for tomorrow. Kidding, Julien, kidding.
I get it.
Those are things that we're super excited about, but due to the complexity, not all of them will get to the goal line.
Appreciate it. All right, guys. I'll let it be. Thank you so much. Best of luck.
Thanks, Julian.
Speaker 4
Thank you. Now we're going to take our next question. The question comes to the line of Nicholas Campanella from Buckley. Your line is open. Please ask your question.
Hey, good morning. Big, big, big Larry David fan, and a Coben fan too. I guess just taking a further step on the backlog, what is your line of sight to kind of convert some of the four gigawatts to actual ESAs? Are you expecting to have more ESAs by the third quarter or the fourth quarter? How would you kind of frame the expectations there?
Speaker 2
We're not, you know, putting, obviously, if we have letters of intent, we're spending serious time, effort and time on this. It's always difficult to put timing on it, but some of these things are in our control and some of them are not. Some of them have to do with when an interconnection study gets finished. If somebody delays an interconnection study two months, there's not a darn thing we can do about it. We are pushing. The reason we want to have a backlog of this size is to make sure that we have significant transactions to continue to tell you about. We're super optimistic, but I don't want to predict quarter by quarter. That's just too, you know, too difficult. I've been in the development business too long. Every time in my career that I've tried to put out a development timeline, I've been wrong.
I don't really like being wrong.
Fair enough. It just seems like on VPP, the adoption rates are coming in better than initially thought in Texas. I'm curious if you can kind of, now that you've had a little bit more time after you've announced this transaction in the first quarter, how do you think the PJM opportunity is shaping up?
I think we need to see the Texas opportunity a little more. Remember, it's only been about three months that we've been in market. The results are great, but we want to make sure we have a complete shakedown cruise and know everything there is to know. Then we will look at certain parts of PJM that we think are particularly ripe for this type of offering. I wouldn't expect it to be this year.
Thank you.
Speaker 4
Thank you. Now we're going to take our next question. The question comes to the line of Angie Sturzynski from Seaport. Your line is open. Please ask your question.
Good morning. Thank you.
Speaker 2
Hi, Angie. How are you?
Very good. First, about the big beautiful bill and its impact on the tax shield, it basically brings with it that deal and the Rockland transaction and how that impacts your free cash flow per share growth trajectory.
Hey, Angie. It's Bruce. Needless to say, the OB3 certainly is a good outcome for us as it relates to those particular transactions. We're still in the process of going through the purchase price allocation and won't obviously be done with that until we close. Based on early estimates, we would expect potential cash savings to be above and beyond what we had originally assumed in our underwriting to be close to $1 billion, if not a little bit more than that, primarily realized over the course of 2027 to 2030.
Okay. That's good. Secondly, I was clearly hoping that you would say that there is a meaningful uptick in the above 14% FFO per share growth trajectory that you were facing on the back of the deal.
I didn't say one way or another, but, you know, obviously, when it comes time for us to update you guys on that, we will do so.
Okay. Secondly, yes, you have a big transaction pending, but we do still see some asset sale, especially in Pennsylvania. I'm just wondering if, in light of the fact that you have a pending transaction, does it preclude you from actually potentially bidding for other assets in PJM? You still have a relatively small footprint in this power market.
No, it does not preclude us, Angie. I mean, I don't think we can take a bite of the same size that we did a couple of months ago, but if there's an attractive asset at the right place and the right price, you will find us there.
Lastly, the asset that just got the TEF commitment and the other assets that are still waiting for that, could we expect data center contracts for these TEF assets, either the ones already awarded the loans or the future ones?
The TEF assets are required to go into the grid. Existing assets, of course, that we already have could be directed from a fungibility point of view, but you could not direct TEF assets to a data center. They have to go into the grid.
Even if, I mean, you could have a front-of-the-meter contract, right, where the power does flow through the grid. It's just that.
Yeah, absolutely, Angie. I mean, look, I think we can supply a data center from all of our existing plants in Texas without a problem. We simply cannot direct a TEF plant as if it's a behind-the-meter deal or being dedicated solely to a data center.
Okay. Just one question. Maybe I'm confused. What is it exactly? What is the difference between the contract that you just signed and the other CNI contracts? Besides the higher margin, obviously, you're not leasing the sites, right? It's not like it's co-located with one of your power plants. Why is it different than any other large-scale CNI contract?
Yeah, Angie, we haven't said whether it's co-located or not. We're not going to be doing that going forward just as a rule. I just want to be clear unless our customer wants to announce that it's co-located, that's fine. I think people are willing to pay premiums at data centers for assurance that they can have 10 to 20 years of power at a price that they know what it's going to be so they can plan accordingly. I think the premium is in large part a result of being able to sign up for 10 years.
Okay. Thank you. Bye-bye.
Thank you, Angie.
Speaker 4
Thank you. Now we're going to take our next question. The question comes to the line of Michael Sullivan from Wolfe Research. Your line is open. Please ask your question.
Hey, good morning, guys.
Speaker 2
Hey, Jolie. How are you?
Hey, hey, doing all right. I had another one on the data center deal you announced today. Just any more color on, you know, maybe why the load ramp is a little bit slower than maybe we would think for something in Texas. I get the sensitivity, but you kind of introduce Fallon and Menlo on the last call, like any reason to think they wouldn't be the ones associated with this?
I'll let Rob take the first part of that, and then I'll grab the second. Go ahead, Rob.
Speaker 1
On this particular transaction that we announced today, this data center design is more modular, and it comes in in pieces. It's not, you know, to compare that to the things you guys are thinking about, the 100-megawatt clips that kind of come in on like a gigawatt site. These are designed, these are edge-type data centers, so they come in in smaller sizes. That's why the ramp looks different than what you might have expected.
It does, yep.
Speaker 2
Paul and Menlo are still in that four-gigawatt letter of intent number that we put out there. We're still working with both of those entities under letters of intent. We're not ready to announce a firm deal with either one of them, but we are still working actively with both of them.
Okay. That's really helpful. In terms of how you're thinking about the cadence of updating your outlook, should we be thinking about Q3 as a standalone update for just 2026? Are you thinking about the long-term plan? When do you officially pull LS Power in there? Do you wait for that to close or give any incremental updates along the way?
I think you'll get NRG alone in the third quarter, on the third quarter call. Until we own LS Power, we can't really put it into our numbers. I would expect that to be maybe in our first, on our year-end call, assuming the transaction is closed by then. If not, it'll be on the first quarter call.
Okay. The NRG that's standalone, is that for 2026 only, or you're doing like a long-term refresh with Q3?
I think, Sally, we'll probably, we'll certainly do '26. Whether we update the outlook or not is going to be a function of what we see at the time. Certainly, you'll get '26. It makes more sense to do it after LS Power is closed. That's probably the more likely time, Sally.
Okay. Fair enough. Thank you.
I think I just made my finance people very happy that they don't have to do a double update by the next quarter, too.
Speaker 4
Excuse me, Michael. Any further questions?
No, I'm all good. Thanks, guys.
Thank you so much. Now we're going to take our next question. The question comes to the line of Carly Davenport from Goldman Sachs. Your line is open. Please ask your question.
Speaker 0
Hey, good morning. Thanks for taking the questions.
Speaker 2
Hi, Carly. How are you?
Speaker 0
Hey, doing well, thanks. How are you?
Speaker 2
Good, thank you.
Speaker 0
We wanted to just ask a couple of follow-ups. First on the virtual power plant opportunity, obviously, raising the 25 target there. I guess, any more you can expand on the drivers of that strength and if you see any sort of read-throughs to the potential longer-term glide path?
Speaker 2
I think it's still early days, and we're still really analyzing the speed of the takeup. We were always super optimistic, but it's been faster than we expected. We need to see whether this is just early startup momentum or sustainable before we think about changing any kind of numbers or guidance. What we are seeing is a tremendous amount of uptake of the program, as well as the equally interesting people who are taking additional Vivint Smart Home pieces and products and putting them into their homes. It's great cause for optimism, and I hope, in maybe the next call or the one after that, we'll be able to give a little bit more clarity on what the drivers are. I'm a little reluctant to do it after only three months in the market.
Speaker 0
Got it. Okay. Fair enough. That all makes sense. Any updates to share on the partnership with GE Vernova and Kiewit on the gas assets to kind of start up in that 2029-2030 timeframe? I guess, how's development progressing there? Are those plans part of the discussions that you're having with potential data center customers?
Speaker 2
Yeah. I mean, that partnership is very closely related to the pipeline that we put on the right side of the slide there. As some of those letters of intent, the joint development agreements advance, we bring GE Vernova and Kiewit along with us for the ones where their power would be required to execute.
Speaker 0
Great. Thank you for the color.
Speaker 4
Thank you. Dear participants, as a reminder, if you wish to ask a question, please press star 11 on your telephone keypad. We are going to take our next question. We are going to take the question from David Arcaro from Morgan Stanley. Your line is open. Please ask your question.
Speaker 3
Hey, thanks so much. Good morning.
Speaker 2
Hi, David.
Speaker 3
Congratulations. Let's see. I was wondering just on this data center agreement here, could you clarify, is the margin fixed over the cost of supply for this agreement such that it's indexed to the market, or is this a long-term fixed price agreement for the customer, maybe with escalators? Just any clarity there would be helpful.
Speaker 2
Yeah. I mean, we've done a bunch of things to lock in the margin, David, to keep it at the level so that it will maintain a level as if we were pricing it at the numbers that we said today. We're not going to tell people how we do that because it's part of our secret sauce. If you look at what we put out as a pricing number, and you can, pricing in Texas as well as anybody, you can see what the margin is, and that margin is well protected over the course of the agreement.
Speaker 3
Got it. Understood. Okay, that's helpful. A little bit related to the prior question, just what are you seeing in terms of interest in additionality in the market, in terms of the portfolio of solutions here for data centers? We've seen them go a bunch of different directions. What's the current appetite and push for bringing additionality here?
Speaker 2
Look, I think there's still a tremendous appetite for additionality, partly for assurance from people that they can have power and partly because grids are tight. Both of those are factors that are going to lead to a stronger and stronger push for additionality going forward. We feel very good about the fact that we have the agreement with GE Vernova and Kiewit in order to bring that additionality to bear. We think it will be well received both by regulators and by end users.
Speaker 3
Yeah, absolutely. You're in a unique position there. If you don't mind, Rob, could I bug you for just your current outlook for power prices in Texas? I mean, we're seeing continued acceleration in data center activity, load growth from different angles. How are you expecting power prices to trend as you see it today?
Speaker 1
I'm going to sound like a broken record, David. The power prices, we've seen an upward movement in the off-peaks, which would be driven by kind of the support of large industrial loads, CNI, AI, all those things. The forecasts still don't reflect what should be reflected in them. The reason for that, or at least one potential reason for that, is we're waiting on data points. We're waiting on load to get announced and show up. The back of the curve is going to see that and then move. Because of the work that got done with Texas Senate Bill 6, ERCOT's forecast will start to reflect reality again. If the ERCOT report says 200 gigawatts of load, the market doesn't move. If a real report said 30 gigawatts of load, this market would jump $10. We still see plenty of upside in the curves in Texas.
Speaker 3
Great. Appreciate it. Thanks so much.
Speaker 4
Thank you. The speakers are on the further questions for today. I would now like to hand the conference over to Lawrence Coben for any closing remarks.
Speaker 2
I want to thank you all for your interest in NRG and for being a part of this call. We are super excited about where we stand and even more excited about where we're going. Thank you for your interest and look forward to seeing you all soon.
Speaker 4
Ladies and gentlemen, thank you for your participation in today's conference. This concludes the program.