Research analysts who have asked questions during SILVERCORP METALS earnings calls.
Recent press releases and 8-K filings for SVM.
Silvercorp Metals Inc. Updates El Domo Project Budget and Schedule
SVM
New Projects/Investments
Guidance Update
- Silvercorp Metals Inc. has updated the construction budget for its El Domo Project to $284 million, an increase of $44 million from the previous $240 million estimate as of March 31, 2025.
- The project's production schedule has been delayed by six months, with production now anticipated by July 1st, 2027, instead of early-2027.
- The budget increase is primarily due to a $16 million rise in VAT, $15 million for equipment and material purchases (including previously missing items and higher logistics costs), and $10.1 million for previously missing items like Engineer of Record and QA/QC supervision. These increases were partially offset by a $15 million reduction in contingency and $4.2 million decrease in Package #2 Mining and Stripping costs.
- In 2025, $44.5 million was spent on the project, and the company ordered most long-lead time major equipment, including 14MW diesel generator sets to ensure power availability for commissioning in July 2027, regardless of the external powerline status.
2 days ago
Silvercorp Metals Updates El Domo Project Budget and Schedule
SVM
New Projects/Investments
Guidance Update
- Silvercorp Metals Inc. has updated the construction budget for its El Domo Project to $284 million, an increase of $44 million compared to the $240 million estimate from March 31, 2025.
- The primary drivers for the budget increase include a $16 million rise due to a revised VAT rate, a $15 million increase in equipment and material purchases for the process plant, and a $7.2 million increase for the construction and installation of the process plant.
- The El Domo Project is now scheduled to be in production by July 1st, 2027, representing a six-month delay from the previous early-2027 estimate.
- In 2025, $44.5 million was spent on the project, achieving significant progress in site preparation, archaeological clearance, and road infrastructure.
2 days ago
Silvercorp Metals Inc. Reports Preliminary Economic Assessment for Condor Gold Project
SVM
New Projects/Investments
Guidance Update
- The Independent Technical Report for the Condor Gold Project, published on January 30, 2026, projects a 13-year mine life with a nominal production rate of 1.8 million tonnes per annum. Silvercorp Metals Inc. owns 98.73% of the project.
- A Preliminary Economic Assessment (PEA) for the project, based on a $2,600/oz gold price, estimates a post-tax NPV5% of $522M and a post-tax IRR of 29%, with initial capital costs of $292M.
- As of November 30, 2025, the project's Indicated Mineral Resources total 14.8 Mt and Inferred Mineral Resources total 50.1 Mt. It is important to note that no mineral reserves have been declared for the project, as the PEA is preliminary and includes inferred mineral resources.
3 days ago
Silvercorp Completes Acquisition of Tulkubash/Kyzyltash Gold Projects
SVM
New Projects/Investments
M&A
- Silvercorp Metals Inc. completed the acquisition of a 70% interest in Chaarat ZAAV CJSC for US$162 million in January 2026.
- This acquisition includes the fully-permitted Tulkubash/Kyzyltash gold projects and surrounding exploration licenses in the Tian Shan area of the Kyrgyz Republic.
- Silvercorp will convert ZAAV into a joint venture company (JVC) with Kyrgyzaltyn, holding a 70% interest and operating the JVC, while Kyrgyzaltyn will hold a 30% free-carried interest.
- The company plans a two-phase development for the projects, with Phase 1 (2026-2028) for Tulkubash 1 involving a US$150 million investment and expected annual gold production of approximately 110,000 oz for 3-4 years starting 2027-2028.
- Phase 2 (2028-2031) for Kyzyltash 1 is projected to involve a US$400 million investment and produce approximately 190,000 to 230,000 oz of gold annually for over 18 years, starting from 2031.
4 days ago
Silvercorp Completes Acquisition of Tulkubash/Kyzyltash Gold Projects
SVM
M&A
New Projects/Investments
- Silvercorp Metals Inc. completed the acquisition of Chaarat ZAAV CJSC, which holds the Tulkubash/Kyzyltash gold projects in Kyrgyzstan, for a $92 million payment to Chaarat Gold Holdings Limited.
- Silvercorp will convert ZAAV into a joint venture company (JVC) with Kyrgyzaltyn, holding a 70% operating interest while Kyrgyzaltyn holds a 30% free-carried interest.
- The JVC plans to extend the mining license validity period to June 25, 2062, after which Silvercorp will make an additional $60 million cash payment to the National Investment Agency.
Jan 27, 2026, 11:18 PM
Silvercorp Completes Acquisition of Tulkubash/Kyzyltash Gold Projects
SVM
M&A
New Projects/Investments
- Silvercorp Metals Inc. has completed the acquisition of Chaarat ZAAV CJSC, making a $92 million payment to Chaarat after the Kyrgyz government waived its pre-emptive right.
- Silvercorp will convert ZAAV into a joint venture company (JVC) with Kyrgyzaltyn, holding a 70% operating interest while Kyrgyzaltyn holds a 30% free-carried interest.
- The JVC will apply to extend the mining license for the Tulkubash/Kyzyltash gold projects from June 25, 2032, to June 25, 2062.
- Following the license extension, Silvercorp will make a $60 million cash payment to the National Investment Agency.
- ZAAV holds a 100% interest in the mining license for the fully-permitted Tulkubash/Kyzyltash gold projects and surrounding exploration licenses in the Tian Shan area.
Jan 27, 2026, 10:05 PM
Silvercorp Metals Inc. Acquires 70% Interest in Tulkubash/Kyzyltash Gold Projects
SVM
M&A
New Projects/Investments
- Silvercorp Metals Inc. (SVM) has signed agreements to acquire a 70% interest in the Tulkubash/Kyzyltash gold projects in Kyrgyzstan for a cash consideration of US$162 million.
- The acquisition establishes a joint venture where Silvercorp will hold a 70% interest and be the operator, with Kyrgyzaltyn holding a 30% free-carried interest.
- The projects have a two-phase development plan: Phase 1 (2026-2028) for Tulkubash 1 involves a US$150 million investment to produce approximately 110,000 oz of gold annually for 3-4 years, and Phase 2 (2028-2031) for Kyzyltash 1 involves approximately US$400 million investment to produce 190,000 to 230,000 oz of gold annually for over 18 years.
- Silvercorp plans to fund the acquisition using existing cash and short-term investments, and Phase 1 development through remaining cash, operational cash flow, and financing capacity.
Jan 20, 2026, 11:56 PM
Silvercorp Metals Acquires 70% Interest in Tulkubash/Kyzyltash Gold Projects
SVM
New Projects/Investments
M&A
- Silvercorp Metals Inc. has acquired a 70% interest in Chaarat ZAAV CJSC, which holds the Tulkubash/Kyzyltash gold projects in the Kyrgyz Republic, for a cash consideration of US$162 million.
- This acquisition will form a joint venture where Silvercorp will hold a 70% interest and operate the projects, with Kyrgyzaltyn holding a 30% free-carried interest.
- The development plan includes two phases: Phase 1 (2026-2028) involves a US$150 million investment for Tulkubash, targeting approximately 110,000 oz of gold annually for 3-4 years starting 2027-2028; Phase 2 (2028-2031) involves a US$400 million investment for Kyzyltash, aiming for approximately 190,000 to 230,000 oz of gold annually for over 18 years starting 2031.
- Silvercorp intends to fund the acquisition and initial development using its existing cash and short-term investments.
Jan 20, 2026, 12:30 PM
Silvercorp Metals Inc. Reports Q3 Fiscal 2026 Operational Results and Revenue Growth
SVM
Earnings
Revenue Acceleration/Inflection
New Projects/Investments
- Silvercorp Metals Inc. achieved record revenue of approximately $126.1 million in Q3 Fiscal 2026, marking a 51% increase over Q3 Fiscal 2025.
- For Q3 Fiscal 2026, the company reported a 4% decrease in silver production and a 4% decrease in lead production, while zinc production increased by 5% compared to Q3 Fiscal 2025. Specific production volumes are detailed in the table below.
- Consolidated ore processed in Q3 Fiscal 2026 was 415,520 tonnes.
- Silvercorp expects to release its Q3 Fiscal 2026 unaudited interim financial results on Monday, February 9, 2026, after market close.
| Metric | Q3 Fiscal 2026 | Q3 Fiscal 2025 |
|---|---|---|
| Silver Production (million ounces) | 1.9 | 1.9 |
| Lead Production (million pounds) | 16.4 | 17.1 |
| Zinc Production (million pounds) | 7.0 | 6.7 |
Jan 16, 2026, 1:06 AM
Silvercorp Reports Q3 Fiscal 2026 Production and Sales Figures
SVM
Earnings
Revenue Acceleration/Inflection
- Silvercorp Metals Inc. (SVM) reported record revenue of approximately $126.1 million for the third quarter ended December 31, 2025 (Q3 Fiscal 2026), representing a 51% increase over Q3 Fiscal 2025.
- For Q3 Fiscal 2026, silver production was 1.9 million ounces, a 4% decrease compared to Q3 Fiscal 2025, and lead production decreased by 4% to 16.4 million pounds.
- Zinc production for Q3 Fiscal 2026 increased by 5% to 7.0 million pounds.
- Silvercorp expects to release its Q3 Fiscal 2026 unaudited interim financial results on Monday, February 9, 2026.
Jan 15, 2026, 10:05 PM
Quarterly earnings call transcripts for SILVERCORP METALS.
Ask Fintool AI Agent
Get instant answers from SEC filings, earnings calls & more